S.No | Activity taken upon musteroll | Quantity | Unit Price | Total |
1 | Ordinary shrub jungle (areas below 25% covered by shrubs) clearance involving removal of grass. Shrubs, bushes and twigs, excluding uprooting (for survey works) | 0 | 0 | 0 |
2 | Earth work in bulk excavation (exceeding 30cm in depth, 1.5m in width as well as 10sqm on plan) including disposal of excavated soil lead upto 50m and lift upto 1.5m, disposed soil to be levelled and neatly dressed.-Loose or soft soil | 43.19 | 86.25 | 3725.1375 |
3 | Earth work in rough excavation, filling excavated earth into depressions on banking as directed, top surface to be levelled and neatly dressed.-Loose or soft soil | 225 | 55.8 | 12555 |
4 | Extra for every additional Lead beyond 50metres or part thereof upto 200 m for every 50 m lead | 140.63 | 21.9 | 3079.797 |
5 | Providing and placing in position RCC for roof, beams, columns column footing lintels chhajjas, balcony, stairs etc, excluding cost of reinforcement & centring but including finishing & curing.-CC 1:2:4 (1cement, 2sand, 4graded stone aggregate 20 mm nominal size) | 6.33 | 3418 | 21635.94 |
6 | False work for R.C.C. and P.C.C. work in plinth and foundation | 127 | 154.2 | 19583.4 |
7 | Providing and placing in position tested steel for R.C.C. work including cutting, bending, binding etc. as per drawings and placing in position complete up to floor two level including cost of binding wire and all wastage etc. complete.-Cold twisted / Hot rolled deformed / Thermo mechanicaly treated steel bars | 178 | 65.9 | 11730.2 |
8 | Transportation of metal | 5.38 | 214.5 | 1154.01 |
9 | Transportation of metal | 9.13 | 193.05 | 1762.5465 |
10 | FOR EARTHEN DAM - Construction of rock toe in earthen embankments including laying and hand packing, dressing, wedging and finishing over surface with.-Black trap, basalt or granite | 13.5 | 418.1 | 5644.35 |
11 | Earth work for well excavation including disposal of excavated soil lead upto 50m and lift upto 1.5m, disposed soil to be levelled and neatly dressed.-Dense or hard soil | 27.17 | 90.1 | 2448.017 |
12 | Earth work for well excavation including disposal of excavated soil lead upto 50m and lift upto 1.5m, disposed soil to be levelled and neatly dressed.-Hard Moorum | 27.17 | 117.1 | 3181.607 |
13 | Earth work for well excavation including disposal or stacking of excavated soil lead upto 50m lift upto 1.5m-Disintegrated or soft rock (not requiring blasting) | 54.34 | 273.1 | 14840.254 |
14 | Earth work for well excavation including disposal or stacking of excavated soil lead upto 50m lift upto 1.5m-Hard rock requiring blasting. | 254 | 479.9 | 121894.6 |
15 | Extra rates for quantities of work executed. In or under water or in foul condition (extra rate for the main item concerned is allowed on account of slow progress of works) | 396.83 | 12.6 | 5000.058 |
16 | work charge | 109.56 | 100 | 10956 |