State: MADHYA PRADESH District: KATNI Block: DHIMERKHEDA Panchayat: PADRBHATA
Work Code: 1744006059/RC/22012034222501 (p c c road avam nali nirman kallu darbhaan ke ghar)
Work Category: Rural Connectivity
Note:
Total Material cost and Total Activity cost shown absolute value which is multiples of 100/1000!
Financial Year : 2014-2015 Execution Level : GP
Execution Agency : Gram Panchayat(3) Work Status : Approve
Included in Annual Plan : Yes Perspective Plan : Yes
Proposal Date : 25/4/2014 Work start date : 20/6/2014
Present status : Earthern road Proposed Status : Cement Concrete
Tech Sanction Details
Technical Sanction No. : 101/59 Sanction Date : 22/5/2014
Estimated Cost as per Tech. Detl (in Rs.)
Unskilled Material Contingency Total
Est. Material Cost Est. Skilled Cost Est. Semi-Skilled Cost Panchparmeshwar scheme2 scheme3 Total
105000 69000 0 0 297000 0 0 366000 0 471000
Financial Sanction Details
Financial\Administrative Sanction No: 03/59 Financial\Administrative Sanction Date 25/5/2014
Fin. Sanc. Amt. (in Rs) NREGA:174000 Panchparmeshwar
297000
Scheme 2
0
Scheme 3
0
Total
471000
S.NoActivity taken upon musterollQuantityUnit PriceTotal
1Dag-beling-Double spade "v" shaped stroke 100mm deep4350.4174
2Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundation etc. in layers not exceeding 20cm in depth consolidating each deposited layers by ramming and watering lead upto 50m and lift upto 1.5m98.632.43194.64
3Providing and laying in foundation, plinth and under floors cement concrete with 40mm nominal size graded stone aggregates (metal) i/c ramming in layers and curing complete excluding cost of form work-C.C. 1:2:4 (1cement, 2sand, 4metal)69.962846.06199110.3576
4Providing and laying in foundation, plinth and under floors cement concrete with 40mm nominal size graded stone aggregates (metal) i/c ramming in layers and curing complete excluding cost of form work-C.C. 1:3:6 (1cement, 3sand, 6metal)52.722250.09118624.7448
5Add to item No. 0413 and 0415 if in place of 40mm metal.-If 20 mm graded metal is used69.96149.210438.032
6False work for R.C.C. and P.C.C. work in plinth and foundation261.58132.334607.034
7Providing and filling in position blown bitumen in expansion joints (10cm deep and 1cm Wide)427.7562566.5
8Transportation charges of water for every additional 200m or part thereof, beyond initial lead of 200m up to 2 Km. Lead for 98.68.2808.52
9Transportation charges of water for every additional 200m or part thereof, beyond initial lead of 200m up to 2 Km. Lead for 122.6836.24441.016
10Transportation of 20 MM metal108.9300.632735.34
11Add if Lead is more than 5.00Km-For every 0.5 Kms. Lead beyond 5 Kms. and part there of upto 10 Kms.152.97128.0719590.8679
12Transportation rates for Moorum, sand, earth, surkhi, fly ash, cement and mortars.23.2280.086497.856
13Loading of metal in truck, dumper etc.98.623.112278.646
14Unloading of metal in truck, dumper etc.98.611.881171.368
15Earth work in bulk excavation (exceeding 30cm in depth, 1.5m in width as well as 10sqm on plan) including disposal of excavated soil lead upto 20m and lift upto 1.5m, disposed soil to be levelled and neatly dressed -Dense or hard soil for Road Work281.373.420647.42
16Collection of hard moorum including stacking at quarry.98.6118.311664.38
17SIGN BOARD120002000
Total Activity 471000
S.NoMaterialQuantityUnit PriceTotal
120 MM B.T.METAL59.93120071916
240 M.M. METAL47.41649.1430775.7274
3CEMENT(BEGS)659280184520
4Centering and Shuttering236.8580.919161.165
5Display board120002000
6joint filler for fixed427.7562566.5
7MIxer Vibrator63001800
8mixer machin (perday)66003600
9sand cum53.6560032190
10Transportanion of hard Muram98.6128.0712627.702
11transpotion of water122.6836.24441.016
Total Material 366000