S.No | Activity taken upon musteroll | Quantity | Unit Price | Total |
1 | Site clearance, cutting grass, raking into heaps and removing off the premises | 0 | 0 | 0 |
2 | Earth work in bulk excavation (exceeding 30cm in depth, 1.5m in width as well as 10sqm on plan) including disposal of excavated soil lead upto 50m and lift upto 1.5m, disposed soil to be levelled and neatly dressed.-Loose or soft soil | 6.75 | 81.2 | 548.1 |
3 | Providing and laying in foundation, plinth and under floors cement concrete with 40mm nominal size graded stone aggregates (metal) i/c ramming in layers and curing complete excluding cost of form work-C.C. 1:2:4 (1cement, 2sand, 4metal) | 0.119 | 3007.5 | 357.8925 |
4 | Providing and laying in foundation, plinth and under floors cement concrete with 40mm nominal size graded stone aggregates (metal) i/c ramming in layers and curing complete excluding cost of form work-C.C. 1:3:6 (1cement, 3sand, 6metal) | 1.482 | 2343.8 | 3473.5116 |
5 | Add to item No. 0413 and 0415 if in place of 40mm metal.-If 20 mm graded metal is used | 0.119 | 226.8 | 26.9892 |
6 | Class 25 open bhatta or pajawa burnt brick masonry in plinth and foundation.-Cement mortar 1:4 (1cement, 4sand) | 4.818 | 2334.4 | 11247.1392 |
7 | Class 25 open bhatta or pajawa burnt brick masonry in plinth and foundation.-Cement mortar 1:5 (1cement, 5sand) | 1.625 | 2250.9 | 3657.7125 |
8 | 15mm thick cement plaster on rough side of wall in-Cement mortar 1:6 (1cement, 6sand) | 23.3 | 85.8 | 1999.14 |
9 | Providing corrugated C.I. sheet of class III roofing fixed with galvanised iron J or L hooks bolts and nuts 8mm diameter with bitumen and G.I. limpet washers or with complete excluding the cost of purlins, rafters and trusses.-0.63 mm thick sheet. | 10.8 | 749.8 | 8097.84 |
10 | Transportation of metal | 1.44 | 368.4 | 530.496 |
11 | Transportation of sand | 2.72 | 331.56 | 901.8432 |
12 | Transportation rates for Bricks, kanker, stone chips shingle & excavated materials in disintegrated rock & soft rock. | 7.54 | 440 | 3317.6 |
13 | Transportation rates for Moorum, sand, earth, surkhi, fly ash, cement and mortars. | 1.875 | 259.56 | 486.675 |
14 | Collection of hard moorum including stacking at quarry. | 1.875 | 130.8 | 245.25 |
15 | work charge | 1 | 1568 | 1568 |
16 | contingency | 1 | 3300 | 3300 |
17 | TRANSPOTATION OF CEMENT | 0.58 | 259.56 | 150.5448 |