S.No | Activity taken upon musteroll | Quantity | Unit Price | Total |
1 | Orissa pattern W.C. pan of size 580x440 mm | 0 | 0 | 0 |
2 | Excavation in earth for hard murum type of strata including dressing and conveying the excavated material by head load upto a distance of 10m and laying or spreading or filling in furrahas in layers of 30cm thick upto a lift of 1.50 m as directed. (A) Excavation - (In General) rate for other area | 4.46 | 174.609865470852 | 778.76 |
3 | Conveying soft/hard murum/silt/sand/grit or all sorts of soil at the work site, from the collected stacks, spreading, laying and sectioning / dressing etc. complete. (does not include lead)
Rate for the other area | 0 | 0 | 0 |
4 | Providing and casting in situ PCC M15 grade of trap metal for
coping to head walls / parapet including centering, form work,
compaction and curing etc. complete. (with reversible drum
type mixer with SCADA with natural sand) | 0.52 | 4753.48076923077 | 2471.81 |
5 | Providing and fixing black kadappa stone shelves 25mm. thick machine polished, ex10.00ding the polish upto 20 cm
As per e-DSR- 33.23/183
Specifications: Bd.M.29 Page No. 391 | 0 | 0 | 0 |
6 | Providing and fixing 6.00 mm thick ISI mark Asbestos Cement
Corrugated sheet roofing including galvanised iron J or L
hook bolts galvanised iron band bituminous G.I. washers,
galvanised iron clamps, bolts, nuts and scaffolding etc.
complete. | 0 | 0 | 0 |
7 | Providing and fixing factory made paneled door shutter in single leaf 35 mm thick style and rail without ventilator with Country T.W.
panels 12 mm thick including wrought iron hold fast and stainless steel fixtures with oil painting 3 coats etc. complete. | 0 | 0 | 0 |
8 | Providing Laterite stone Masonry in Cement Mortar 1:6 in Foundation and plinth including racking out joints when plastering is to be done / striking joints when no plastering is to be done watering and scaffolding. | 2.01 | 4334.28855721393 | 8711.92 |
9 | Providing Laterite stone Masonry in Cement Mortar 1:6 in Superstructure including racking out joints when plastering is to be done / striking joints when no plastering is to be done watering and scaffolding. | 0.01 | 3246 | 32.46 |