S.No | Activity taken upon musteroll | Quantity | Unit Price | Total |
1 | signboard | 1 | 2000 | 2000 |
2 | Site clearance, cutting grass, raking into heaps and removing off the premises | 0 | 1.6 | 0 |
3 | Lime Surkhi Mortar 1:1:2 ( 1 lime putty, 1 surkhi, 2sand ) | 1170 | 52.7 | 61659 |
4 | Work charge | 1 | 2000 | 2000 |
5 | Dag-beling-Single spade stroke minimum 75mm deep | 3000 | 0.3 | 900 |
6 | Labour only for 20mm thick cement plaster of any ratio. | 8000 | 1.8 | 14400 |
7 | Collection of approved soil having CBR not less then 12, including stacking at quarry. | 350 | 52.7 | 18445 |
8 | Transportation of metal | 2950 | 119 | 351050 |
9 | Compaction of embankment with approved materials as per clause 301.4 & 301.5 of specifications for rural roads(MORD), already spreaded at site, obtained from roadway cutting, excavated from drains, foundation of other structures or from borrow pit, making | 1170 | 21.6 | 25272 |
10 | Compaction of soil for construction of subgrade & earthen shoulders with approved material, already spreaded at site, obtained from roadway cutting, drains, foundation of other structures or barrow pits, i/c making 4% camber and required grade by tractor | 2571 | 23.1 | 59390.1 |
11 | Compaction of hard shoulder collected at site, i/c making 4-5% camber by tractor mounted grader or labourers, watering at OMC and compacting with 80 to 100 kN static weight rollers to achieve desired density minimum 100% of the MDD as per IS:2720 (Part-7) | 350 | 40.1 | 14035 |
12 | Construction of gravel base course by naturally occurred gravel or river born material or by crushed metal or mixture of two or more to bring the material in appropriate grading confirming to clause 2.2.2.2, plasticity characteristics of fines as per clau | 540.75 | 576.9 | 311958.675 |
13 | Construction of gravel surface course by naturally occurred gravel or river born material or by crushed metal or mixture of two or more in appropriate grading confirming to clause 2.2.2.2, plasticity characteristics of fines as per clause 2.2.3 of IRC:SP: | 154.5 | 508.6 | 78578.7 |
14 | Collection of puddle earth including stacking at quarry | 2571 | 52.7 | 135491.7 |
15 | Labour difference in case of old SoR | 1 | 24151 | 24151 |