S.No | Activity taken upon musteroll | Quantity | Unit Price | Total |
1 | signboard | 1 | 4250 | 4250 |
2 | Dag-beling-Double spade "v" shaped stroke 100mm deep | 510 | 0.4 | 204 |
3 | Filling foundation and around masonry work with moorum I/c ramming layers and watering. | 104.04 | 378.6 | 39389.544 |
4 | Providing and laying in foundation, plinth and under floors cement concrete with 40mm nominal size graded stone aggregates (metal) i/c ramming in layers and curing complete excluding cost of form work-C.C. 1:4:8 (1cement, 4sand, 8metal) | 112.71 | 2511.5 | 283071.165 |
5 | False work for R.C.C. and P.C.C. work in plinth and foundation | 257.89 | 129.6 | 33422.544 |
6 | Providing and filling in position blown bitumen in expansion joints (10cm deep and 1cm Wide) | 127.5 | 5.8 | 739.5 |
7 | Transportation charges of water for every additional 200m or part thereof, beyond initial lead of 200m up to 2 Km. Lead for | 104.04 | 4.8 | 499.392 |
8 | Transportation charges of water for every additional 200m or part thereof, beyond initial lead of 200m up to 2 Km. Lead for | 112.71 | 26.8 | 3020.628 |
9 | Transportation of metal | 95.769 | 511.2 | 48957.1128 |
10 | Transportation rates for Moorum, sand, earth, surkhi, fly ash, cement and mortars. | 1 | 32703 | 32703 |
11 | Earth work in excavation in trenches for foundations and for pipes, cables etc. not exceeding 1.5m in width and for shafts, cesspits and the like not exceeding 10sqm on plan including dressing of sides and ramming of bottoms lift upto 1.5m including getti | 76.5 | 81.6 | 6242.4 |
12 | Preparation of sub grade by excavating earth work to the 15cm average depth, dressing to camber including making good the undulations etc. and disposal of surplus earth with lead upto 20metres and upto 1.5metre.-Loose or soft soil. | 520.2 | 10.7 | 5566.14 |
13 | contingency | 1 | 28935 | 28935 |