S.No | Activity taken upon musteroll | Quantity | Unit Price | Total |
1 | Jungle clearance including uprooting of rank vegetation, grass, brush wood, saplings and tree not exceeding 30cm girth and removing not exceeding 50meters outside the periphery of the area cleared. | 240 | 6.54195833333333 | 1570.07 |
2 | (a) C.C. 1:2:4 (1cement, 2sand, 4metal) | 30.56 | 3816.21858638743 | 116623.64 |
3 | (b) C.C. 1:3:6 (1cement, 3sand, 6metal) | 201.78 | 3162.88606403013 | 638207.15 |
4 | Centering and shuttering including strutting , propping etc. and removal of form work for P.C.C. work in foundation, footing, bases for column | 221.6 | 160.519720216606 | 35571.17 |
5 | (XXI) 22 Km. Lead | 198.41 | 337.682122876871 | 66999.51 |
6 | (XVIII) 16 Km. Lead | 35.16 | 256.827929465302 | 9030.07 |
7 | (XXII) 24 Km. Lead | 96.48 | 319.609141791045 | 30835.89 |
8 | b (iii) Dense or hard soil for Tank Work | 83.52 | 134.1875 | 11207.34 |
9 | a (i) Disintegrated or soft rock (not requiring blasting) for Tank Work | 81.2 | 568.948275862069 | 46198.6 |
10 | b (i) Hard rock requiring blasting for Tank Work | 67.36 | 593.747773159145 | 39994.85 |
11 | Citizen Information Board Size 0.9 Meter x 1.2 Meter ( Community Works ) | 1 | 3603.48 | 3603.48 |