S.No | Activity taken upon musteroll | Quantity | Unit Price | Total |
1 | Contingency | 1 | 23950.9 | 23950.9 |
2 | Dag-beling-Single spade stroke minimum 75mm deep | 600 | 0.2 | 120 |
3 | Transportation rates for Moorum, sand, earth, surkhi, fly ash, cement and mortars. | 810 | 191.16 | 154839.6 |
4 | Rolling & Compaction of granular sub-base of well graded material, spreading in uniform layers with tractor mounted grader on prepared surface, mixing by mix in place, sprinkling of water till OMC, and compacting with smooth wheel rollers of 80 to 100 kN | 1485 | 69.7 | 103504.5 |
5 | Earth work in bulk excavation (exceeding 30cm in depth, 1.5m in width as well as 10sqm on plan) including disposal of excavated soil lead upto 20m and lift upto 1.5m, disposed soil to be levelled and neatly dressed -Dense or hard soil for Road Work | 337.5 | 81.2 | 27405 |
6 | Collection of hard moorum including stacking at quarry. | 810 | 130.8 | 105948 |
7 | Preparation of sub grade by excavating earth work to the 15cm average depth, dressing to camber including making good the undulations etc. and disposal of surplus earth with lead upto 20metres and upto 1.5metre.-Dense or hard soil. | 5400 | 12.8 | 69120 |