S.No | Activity taken upon musteroll | Quantity | Unit Price | Total |
1 | Dag-beling-Single spade stroke minimum 75mm deep | 230 | 0.3 | 69 |
2 | Providing and laying in foundation, plinth and under floors cement concrete with 40mm nominal size graded stone aggregates (metal) i/c ramming in layers and curing complete excluding cost of form work-C.C. 1:2:4 (1cement, 2sand, 4metal) | 80.5 | 3307.4 | 266245.7 |
3 | False work for R.C.C. and P.C.C. work in plinth and foundation | 138 | 147.8 | 20396.4 |
4 | Collection of approved soil having CBR not less then 12, including stacking at quarry. | 67.28 | 142.5 | 9587.4 |
5 | Transportation of metal | 68.43 | 462.23 | 31630.3989 |
6 | Transportation rates for Moorum, sand, earth, surkhi, fly ash, cement and mortars. | 119.6 | 169.803 | 20308.4388 |
7 | Preparation of sub grade by excavating earth work to the 15cm average depth, dressing to camber including making good the undulations etc. and disposal of surplus earth with lead upto 50metres and upto 1.5metre.-Loose or soft soil | 448.5 | 14 | 6279 |
8 | Labour only for moorum, kankar, shingle/ gravel/red bajri spreading levelling to gradient and required camber including dressing. | 67.28 | 44.7 | 3007.416 |
9 | SIGN BOARD | 1 | 5000 | 5000 |