S.No | Activity taken upon musteroll | Quantity | Unit Price | Total |
1 | Earth work in bulk excavation (exceeding 30cm in depth, 1.5m in width as well as 10sqm on plan) including disposal of excavated soil lead upto 50m and lift upto 1.5m, disposed soil to be levelled and neatly dressed.-Loose or soft soil | 24.38 | 89.36 | 2178.5968 |
2 | Earth work in bulk excavation (exceeding 30cm in depth, 1.5m in width as well as 10sqm on plan) including disposal or stacking of excavated soil lead upto 50m lift upto 1.5m-Disintegrated or soft rock (not requiring blasting) | 52.66 | 100.96 | 5316.5536 |
3 | Earth work in excavation in trenches for foundations and for pipes, cables etc. not exceeding 1.5m in width and for shafts, cesspits and the like not exceeding 10sqm on plan including dressing of sides and ramming of bottoms lift upto 1.5m including getti-Hard moorum | 10 | 136.3 | 1363 |
4 | Providing and placing in position tested steel for R.C.C. work including cutting, bending, binding etc. as per drawings and placing in position complete up to floor two level including cost of binding wire and all wastage etc. complete.-Mild steel and Medium tensile steel bars | 83.46 | 3829.15 | 319580.859 |
5 | Providing throating or plaster drip and moulding to R.C.C. chhajja. | 15.46 | 3175.78 | 49097.5588 |
6 | Floor polishing on Masonry or Concrete floors with wax polish of approved brand and manufacture. | 40 | 172.09 | 6883.6 |