State: MADHYA PRADESH District: DAMOH Block: JABERA Panchayat: GHATERA
Work Code: 1711006006/IF/1000066107 (KAPIL DHARA/ RAM SINGH/ CHATUR/GHATERA)
Work Category: Drought Proofing
Note:
Total Material cost and Total Activity cost shown absolute value which is multiples of 100/1000!
Financial Year : 2013-2014 Execution Level : GP
Execution Agency : Gram Panchayat(3) Work Status : Approve
Included in Annual Plan : Perspective Plan :
Proposal Date : 2/10/2013 Work start date : 22/1/2014
Present status : Not Exist Proposed Status : Well
Tech Sanction Details
Technical Sanction No. : 350/06 Sanction Date : 10/1/2014
Estimated Cost as per Tech. Detl (in Rs.)
Unskilled Material Contingency Total
Est. Material Cost Est. Skilled Cost Est. Semi-Skilled Cost Scheme1 scheme2 scheme3 Total
192000 75000 0 0 0 0 0 75000 0 267000
Financial Sanction Details
Financial\Administrative Sanction No: 18/06J Financial\Administrative Sanction Date 20/1/2014
Fin. Sanc. Amt. (in Rs) NREGA:267000 Scheme 1
0
Scheme 2
0
Scheme 3
0
Total
267000
S.NoActivity taken upon musterollQuantityUnit PriceTotal
1signboard120002000
2Contingency610006000
3Dag-beling-Double spade "v" shaped stroke 100mm deep6000.5300
4Extra for every additional Lead beyond 50metres or part thereof upto 200 m for every 50 m lead19521.94270.5
5Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundation etc. in layers not exceeding 20cm in depth consolidating each deposited layers by ramming and watering lead upto 50m and lift upto 1.5m13035.84654
6Labour only for item no. 04048.129.8241.38
7Providing and laying in foundation, plinth and under floors cement concrete with 40mm nominal size graded stone aggregates (metal) i/c ramming in layers and curing complete excluding cost of form work-C.C. 1:2:4 (1cement, 2sand, 4metal)0.583089.91792.142
8Add to item No. 0413 and 0415 if in place of 40mm metal.-If 20 mm graded metal is used0.58169.498.252
9Random / uncoursed rubble masonry in plinth and foundation with mud mortar including levelling at plinth level.571043.659485.2
10Random / uncoursed rubble masonry in plinth and foundation including levelling up with cement concrete 1:6:12 (1cement, 6coarse sand, 12 aggregate 20mm nominal size) at plinth level.-In Cement mortar 1:8 (1cement, 8sand)21835.33670.6
11Labour only for item no.05180.953120.92964.855
12Add extra for brick masonry circular in plan, I/c wells to a mean radius not exceeding 6m (Such as well stening and other similar type of works)60265.515930
13Add to item no.0605 and 0609 for well staining-For every 3meter up to 15 meter depth.92172.315851.6
14TRANSPORTATION OF MATERIAL31100031000
15Pointing on random rubble masonry or uncoursed stone masonry with cement mortar 1:3 (1cement, 3sand)-Ruled pointing2085.11702
16Collection of hard metal other then black trap basalt and granite for road works (without blasting) including stacking as per MOST 1995, clause 400.2.5-Grading - 1 (Size ranging from 90 mm to 45 mm)8.1240.61948.86
17Labour only for boulder soling hand packed excluding consolidation.10.8106.21146.96
18Labour only for spreading, hand packing, and levelling to gradient and required camber as per MOST 2004 clause 404.3.3 of metal, grade-1 As per MOST 2004 clause 400.2.5 including dressing.8.172.9590.49
19Add in item No. 2401 for lift. (In well excavation)-For every 0.50 m after 1.5 m initial depth upto 6.0 m16837.111949.3
20Add in item No. 2401 for lift. (In well excavation)-For every 0.50 m after 6.0 m initial depth upto 10.5 m629.4582.8
21Add in item No. 2402 for lift. (In well excavation)-For every 0.50 m after 1.5 m initial depth upto 6.0 m53810.65702.8
22Add in item No. 2402 for lift. (In well excavation)-For every 0.50 m after 6.0 m initial depth upto 10.5 m38312.94940.7
23Earth work in bulk excavation (exceeding 30cm in depth, 1.5m in width as well as 10sqm on plan) including disposal of excavated soil lead upto 20m and lift upto 1.5m, disposed soil to be levelled and neatly dressed - Dense or hard soil for Well Work302119.736149.4
24Earth work in bulk excavation (exceeding 30cm in depth, 1.5m in width as well as 10sqm on plan) including disposal of excavated soil lead upto 20m and lift upto 1.5m, disposed soil to be levelled and neatly dressed- Dense or hard soil for Tank Work12581.210150
25Earth work in bulk excavation (exceeding 30cm in depth, 1.5m in width as well as 10sqm on plan) including disposal of excavated soil lead upto 20m and lift upto 1.5m, disposed soil to be levelled and neatly dressed.Hard moorum for Well Work83130.210806.6
26Earth work in bulk excavation (exceeding 30cm in depth, 1.5m in width as well as 10sqm on plan) including disposal or stacking of excavated soil lead upto 20m and lift upto 1.5m, disposed soil to be levelled and neatly dressed.Disintegrated or soft rock (not requiring blasting) for Well Work57353.220132.4
27Earth work in bulk excavation (exceeding 30cm in depth, 1.5m in width as well as 10sqm on plan) including disposal or stacking of excavated soil lead upto 20m and lift upto 1.5m, disposed soil to be levelled and neatly dressed.Hard rock requiring blasting for Well Work21477.210021.2
28Collection of boulders at source (maximum size 0.014cum) without quarrying i.e. picked up boulders.10.8100.31083.24
29Collection of sand including screening, washing, stacking and all leads and lifts up to the loading point.8.1139.11126.71
Total Activity 267000
S.NoMaterialQuantityUnit PriceTotal
120 M.M. METAL0.5650325
240 M.M. METAL1.4375525
3Blasting Holas301003000
4Cement95605040
5desal pump rent75003500
6Display board120002000
7First Aid Box1500500
8MASON (PERDAY)4526712015
9Masonry Stone5544024200
10P V C PIPE 21500500
11Photo copy1005500
12Photograph550250
13Sand2.566501664
14Transpotation Charges12096120961
Total Material 75000