S.No | Activity taken upon musteroll | Quantity | Unit Price | Total |
1 | Ordinary shrub jungle (areas below 25% covered by shrubs) clearance involving removal of grass. Shrubs, bushes and twigs, excluding uprooting (for survey works) | 100 | 0.98 | 98 |
2 | Work charge | 1 | 60000 | 60000 |
3 | Earth work in excavation in trenches for foundations and for pipes, cables etc. not exceeding 1.5m in width and for shafts, cesspits and the like not exceeding 10sqm on plan including dressing of sides and ramming of bottoms lift upto 1.5m including getti-Loose or soft soil | 21.6 | 162.25 | 3504.6 |
4 | Steel work welded in built up sections, framed work, including cutting hoisting fixing in position in gratings, frames, guard bars, ladders, railing, brackets and similar works & trusses and trussed purlins up to 25m span and 15 m over all height | 100 | 86.68 | 8668 |
5 | Plantation-Adv-1st Year-Stage-1-RSP | 100 | 15.66 | 1566 |
6 | Plantation-Adv-1st Year-Stage-2-PCP | 3 | 500 | 1500 |
7 | Plantation-Adv-1st Year-Stage-1-CSP | 5 | 750 | 3750 |
8 | Plantation-Adv-1st Year-Stage-3-CSP | 100 | 372 | 37200 |
9 | Plantation-Adv-1st Yar-Stage-4-CSP | 15 | 2000 | 30000 |
10 | SIGN BOARD | 1 | 3500 | 3500 |
11 | Cost of Planting Materials (Seedling) including transportation charges to the Work site. | 3.26 | 100 | 326 |
12 | Planting of seedling followed by watering | 100 | 176.24 | 17624 |
13 | Filling of root tranners with mixing of soil and manure. Mandays per Hundred | 100 | 12.11 | 1211 |