S.No | Activity taken upon musteroll | Quantity | Unit Price | Total |
1 | Earth work in excavation in trenches for foundations and for pipes, cables etc. not exceeding 1.5m in width and for shafts, cesspits and the like not exceeding 10sqm on plan including dressing of sides and ramming of bottoms lift upto 1.5m including getti-Dense or hard soil | 652.5 | 136.31 | 88942.275 |
2 | Transportation of metal | 670.31 | 89.93 | 60280.9783 |
3 | Transportation rates for Moorum, sand, earth, surkhi, fly ash, cement and mortars. | 432.4 | 152.82 | 66079.368 |
4 | Compaction of soil for construction of subgrade & earthen shoulders with approved material, already spreaded at site, obtained from roadway cutting, drains, foundation of other structures or barrow pits, i/c making 4% camber and required grade by tractor | 2000 | 17.37 | 34740 |
5 | Construction of hard shoulder as per clause 407 of specifications for rural roads (MORD), with soil having CBR value not less than 12, inclusive of all leads and lifts, providing 4-5% camber by tractor mounted grader or labourers, watering at OMC and comp | 905.31 | 132.04 | 119537.1324 |
6 | Construction of gravel base course by naturally occurred gravel or river born material or by crushed metal or mixture of two or more to bring the material in appropriate grading confirming to A or B or C of Table 2.1of IRC:SP:77-2008 having CBR not less | 483 | 548.1 | 264732.3 |
7 | Collection of puddle earth including stacking at quarry | 332.4 | 185.38 | 61620.312 |
8 | contingency | 1 | 162067.63 | 162067.63 |