S.No | Activity taken upon musteroll | Quantity | Unit Price | Total |
1 | Site clearance, cutting grass, raking into heaps and removing off the premises | 2200 | 1.8 | 3960 |
2 | Lime Mortar 1:3 ( 1 lime putty, 3sand ) | 551.96 | 46 | 25390.16 |
3 | Boring holes 3.5m deep in ordinary soil (for cast in situ piles) and getting out the soil (under ramming if any shall be paid for separately) and disposal of the surplus excavated soil as directed within a lead of 50m for-Diameter of piles.-250 mm | 6 | 466.5 | 2799 |
4 | Extra for under-ramming inside the bore holes for under reamed piles.-300mm | 12 | 189.2 | 2270.4 |
5 | Providing and laying in foundation, plinth and under floors cement concrete with 40mm nominal size graded stone aggregates (metal) i/c ramming in layers and curing complete excluding cost of form work-C.C. 1:2:4 (1cement, 2sand, 4metal) | 1.367 | 3138.5 | 4290.3295 |
6 | Providing and laying in foundation, plinth and under floors cement concrete with 40mm nominal size graded stone aggregates (metal) i/c ramming in layers and curing complete excluding cost of form work-C.C. 1:3:6 (1cement, 3sand, 6metal) | 1.5 | 2498.6 | 3747.9 |
7 | Providing and placing in position RCC for roof, beams, columns column footing lintels chhajjas, balcony, stairs etc, excluding cost of reinforcement & centring but including finishing & curing.-CC 1:2:4 (1cement, 2sand, 4graded stone aggregate 20 mm nominal size) | 2.72 | 3892.7 | 10588.144 |
8 | False work for lintels slabs, columns, walls, sills, chhajjas balconies, beams, stair cases or ornamental moulded work, curved surface etc. cast in situ including all lead and lift | 187.06 | 210.8 | 39432.248 |
9 | False work for R.C.C. and P.C.C. work in plinth and foundation | 27.48 | 121.4 | 3336.072 |
10 | Steel work in single section including in cutting, hoisting fixing in position in R.S. joists, channels, angles, tee. | 49.57 | 56.7 | 2810.619 |
11 | Providing and placing in position tested steel for R.C.C. work including cutting, bending, binding etc. as per drawings and placing in position complete up to floor two level including cost of binding wire and all wastage etc. complete.-Cold twisted / Hot rolled deformed / Thermo mechanicaly treated steel bars | 648.88 | 53.8 | 34909.744 |
12 | 15mm thick cement plaster on rough side of wall in-Cement mortar 1:6 (1cement, 6sand) | 21 | 117.5 | 2467.5 |
13 | Cement washing (Portland cement) 2 coats.-White cement | 77.96 | 11.6 | 904.336 |
14 | Labour only for-For item no.1315 (a)(b) | 77.96 | 11.6 | 904.336 |
15 | Snowcem or durocem painting of any shade-2 coats on new work | 77.96 | 15 | 1169.4 |
16 | Transportation charges of water for every additional 200m or part thereof, beyond initial lead of 200m up to 2 Km. Lead for | 1648.16 | 16 | 26370.56 |
17 | Transportation of metal | 686.96 | 172.6 | 118569.296 |
18 | Labour only for moorum, screening or binding material as per MOST 2004 clause 400.2.6 spreading on boulder or WBM coat as per MOST 2004 clause 404.2.7 | 686.96 | 46 | 31600.16 |
19 | Compaction of embankment with approved materials as per clause 301.4 & 301.5 of specifications for rural roads(MORD), already spreaded at site, obtained from roadway cutting, excavated from drains, foundation of other structures or from borrow pit, making | 1636.2 | 31.6 | 51703.92 |
20 | Earth work in bulk excavation (exceeding 30cm in depth, 1.5m in width as well as 10sqm on plan) including disposal of excavated soil lead upto 20m and lift upto 1.5m, disposed soil to be levelled and neatly dressed -Dense or hard soil for Road Work | 495 | 91.2 | 45144 |
21 | Earth work in bulk excavation (exceeding 30cm in depth, 1.5m in width as well as 10sqm on plan) including disposal of excavated soil lead upto 20m and lift upto 1.5m, disposed soil to be levelled and neatly dressed - Dense or hard soil for Well Work | 601.2 | 91.2 | 54829.44 |
22 | Collection of hard moorum including stacking at quarry. | 686.96 | 147 | 100983.12 |
23 | contingency | 47322 | 1 | 47322 |