Work Code: 1725007005/LD/22012034298900 (पेयजल कूप निर्माण nirmal nir badgaon piplod)
Work Category: Drought Proofing
Note:
Total Material cost and Total Activity cost shown absolute value which is multiples of 100/1000!
Financial Year : 2016-2017 Execution Level : GP
Execution Agency : Gram Panchayat(3) Work Status : Approve
Included in Annual Plan : Yes Perspective Plan : Yes
Proposal Date : 15/4/2016 Work start date : 18/6/2016
Present status : Existing Proposed Status : Construction of Irrigation Open Well for Community
Tech Sanction Details
Technical Sanction No. : 715*** Sanction Date : 18/1/2017
Estimated Cost as per Tech. Detl (in Rs.)
Unskilled Material Contingency Total
Est. Material Cost Est. Skilled Cost Est. Semi-Skilled Cost Scheme1 scheme2 scheme3 Total
235000 100000 0 0 0 0 0 100000 0 335000
Financial Sanction Details
Financial\Administrative Sanction No: 07 nil### Financial\Administrative Sanction Date 21/1/2017
Fin. Sanc. Amt. (in Rs) NREGA:335000 Scheme 1
0
Scheme 2
0
Scheme 3
0
Total
335000
S.NoActivity taken upon musterollQuantityUnit PriceTotal
1Earth work in bulk excavation (exceeding 30cm in depth, 1.5m in width as well as 10sqm on plan) including disposal of excavated soil lead upto 50m and lift upto 1.5m, disposed soil to be levelled and neatly dressed.-Dense or hard soil187.66512194
2Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundation etc. in layers not exceeding 20cm in depth consolidating each deposited layers by ramming and watering lead upto 50m and lift upto 1.5m67.1235.82402.896
3Providing and placing in position RCC for roof, beams, columns column footing lintels chhajjas, balcony, stairs etc, excluding cost of reinforcement & centring but including finishing & curing.-CC 1:1.5:3 (1cement, 1.5sand, 3graded stone aggregate 20 mm nominal size)13.053897.150857.155
4False work for lintels slabs, columns, walls, sills, chhajjas balconies, beams, stair cases or ornamental moulded work, curved surface etc. cast in situ including all lead and lift151.24199.730202.628
5Providing and placing in position tested steel for R.C.C. work including cutting, bending, binding etc. as per drawings and placing in position complete up to floor two level including cost of binding wire and all wastage etc. complete.-Mild steel and Medium tensile steel bars34065.922406
6Earth work for well excavation including disposal of excavated soil lead upto 50m and lift upto 1.5m, disposed soil to be levelled and neatly dressed.-Dense or hard soil17.0190.11532.601
7Earth work for well excavation including disposal of excavated soil lead upto 50m and lift upto 1.5m, disposed soil to be levelled and neatly dressed.-Hard Moorum39.7117.14648.87
8Earth work for well excavation including disposal or stacking of excavated soil lead upto 50m lift upto 1.5m-Disintegrated or soft rock (not requiring blasting)710.84273.1194130.404
9Earth work for well excavation including disposal or stacking of excavated soil lead upto 50m lift upto 1.5m-Hard rock requiring blasting.000
10work charge15010816200
Total Activity 335000
S.NoMaterialQuantityUnit PriceTotal
1Blasting19014026600
2cement Begs3006018000
3Centering and Shuttering18016028800
4Contangancy1600600
5Display board1500500
6SAND710007000
7STEEL2805014000
8transportion145004500
Total Material 100000