State: MADHYA PRADESH District: NARSINGHPUR Block: BABAI CHICHLI Panchayat: UKASGHAT
Work Code: 1734004009/RC/22012034196565 (पंचपरमेश्वरसीसीरोडनालीनिर्माण(रामकुमारकेघरसेसरजनकौ)
Work Category: Rural Connectivity
Note:
Total Material cost and Total Activity cost shown absolute value which is multiples of 100/1000!
Financial Year : 2012-2013 Execution Level : GP
Execution Agency : Gram Panchayat(3) Work Status : Approve
Included in Annual Plan : No Perspective Plan : No
Proposal Date : 8/2/2013 Work start date : 17/3/2013
Present status : Earthern road Proposed Status : Cement Concrete
Tech Sanction Details
Technical Sanction No. : 1995 Sanction Date : 20/3/2013
Estimated Cost as per Tech. Detl (in Rs.)
Unskilled Material Contingency Total
Est. Material Cost Est. Skilled Cost Est. Semi-Skilled Cost Panchparmeshwar scheme2 scheme3 Total
98100 64200 0 0 335100 0 0 400000 0 497400
Financial Sanction Details
Financial\Administrative Sanction No: 2692 Financial\Administrative Sanction Date 30/3/2013
Fin. Sanc. Amt. (in Rs) NREGA:162300 Panchparmeshwar
335100
Scheme 2
0
Scheme 3
0
Total
498000
S.NoActivity taken upon musterollQuantityUnit PriceTotal
1Contingency182108210
2Providing and laying in foundation, plinth and under floors cement concrete with 40mm nominal size graded stone aggregates (metal) i/c ramming in layers and curing complete excluding cost of form work-C.C. 1:2:4 (1cement, 2sand, 4metal)82.682634.4217812.192
3Providing and laying in foundation, plinth and under floors cement concrete with 40mm nominal size graded stone aggregates (metal) i/c ramming in layers and curing complete excluding cost of form work-C.C. 1:3:6 (1cement, 3sand, 6metal)63.62021.8128586.48
4False work for R.C.C. and P.C.C. work in plinth and foundation143.1139.119905.21
5Add if Lead is more than 5.00Km-For every 0.5 Kms. Lead beyond 30 Kms. and part there of upto 50 Kms.5862136018
6Add if Lead is more than 5.00Km-For every 0.5 Kms. Lead beyond 50 Kms. and part there of upto 100 Kms.71.8162144594.01
7Transportation of sand64.9197.116303.4101
8Transportation rates for Moorum, sand, earth, surkhi, fly ash, cement and mortars.114.4897.1111117.1528
9Labour only for moorum, screening or binding material as per MOST 2004 clause 400.2.6 spreading on boulder or WBM coat as per MOST 2004 clause 404.2.7114.4821.32438.424
10Site clearance, cutting grass, raking into heaps and removing off the premises805.61.51208.4
11Earth work in bulk excavation (exceeding 30cm in depth, 1.5m in width as well as 10sqm on plan) including disposal of excavated soil lead upto 20m and lift upto 1.5m, disposed soil to be levelled and neatly dressed - Dense or hard soil for Well Work12.7273.4933.648
12Collection of soft moorum including stacking at quarry.114.4810211676.96
13Preparation of sub grade by excavating earth work to the 15cm average depth, dressing to camber including making good the undulations etc. and disposal of surplus earth with lead upto 20metres and upto 1.5metre.-Loose or soft soil.763.211.68853.12
Total Activity 498000
S.NoMaterialQuantityUnit PriceTotal
120 MM B.T.METAL71.8131522620.15
240 M.M. METAL5831518270
3CEMENT(BEGS)828.6275227865
4Centering and Shuttering143.188.112607.11
5contengency 21275275
6mason perday16178.172850.72
7mixer machin (perday)610006000
8sand cum64.911157464.65
9Transportaion of muram (trip)71.8162144594.01
10Transportaion of sand (Trip)64.9161.473990.0177
11Transportanion of hard Muram114.4861.477037.0856
12Transportation Cement27.62172.264757.8212
13transportation of 40mm metal5862136018
14Vibrator (Per Day)58004000
15साईनबोर्ड 115001500
Total Material 400000