S.No | Activity taken upon musteroll | Quantity | Unit Price | Total |
1 | Dag-beling-Single spade stroke minimum 75mm deep | 120 | 0.3 | 36 |
2 | Filling foundation or under floor with 40mm gauge graded metal and moorum including ramming in layers and watering. | 12.15 | 882 | 10716.3 |
3 | Providing and laying damp proof course 50mm thick with C.C.1:2:4 with 20mm size graded stone aggregate. including curing. | 81 | 211.4 | 17123.4 |
4 | Random / uncoursed rubble masonry in plinth and foundation including levelling up with cement concrete 1:6:12 (1cement, 6coarse sand, 12 aggregate 20mm nominal size) at plinth level.-In Lime mortar 1:2 (1lime putty, 2sand) | 32.4 | 1858.7 | 60221.88 |
5 | Pointing on random rubble masonry or uncoursed stone masonry with cement mortar 1:4 (1cement, 4sand)-Flush pointing | 72 | 78.5 | 5652 |
6 | Transportation of sand | 1 | 28307.58 | 28307.58 |
7 | Earth work in excavation in trenches for foundations and for pipes,cables etc.not exceeding 1.5 m in width and for shafts,cesspits and the like not exceeding 10 sqm on plan including dressing of sides and ramming of bottoms lift upto 1.5m including gettin-Dense or hard soil | 60.75 | 96.2 | 5844.15 |
8 | contingency | 1 | 6098.69 | 6098.69 |