Govt. of India
Ministry of Rural Development
Department of Rural Development
The Mahatma Gandhi National Rural Employment Guarantee Act 26-Jun-2024 04:37:31 AM 
Back  
State: MADHYA PRADESH District: REWA Block: GANGEV Panchayat: KATAHA
Work Code: 1713004058/RC/22012034299085 (खेत सड़क निर्माण मुख्य मार्ग कटहा से प्राथमिक शाला कटहा तरफ टी यस 2396)
Work Category: Rural Connectivity
Note:
Total Material cost and Total Activity cost shown absolute value which is multiples of 100/1000!
Financial Year : 2015-2016 Execution Level : GP
Execution Agency : Gram Panchayat(3) Work Status : Approve
Included in Annual Plan : Yes Perspective Plan : No
Proposal Date : 29/1/2016 Work start date : 17/2/2016
Present status : No Road Proposed Status : Gravel Road
Tech Sanction Details
Technical Sanction No. : 2396/58 Sanction Date : 15/2/2016
Estimated Cost as per Tech. Detl (in Rs.)
Unskilled Material Contingency Total
Est. Material Cost Est. Skilled Cost Est. Semi-Skilled Cost Scheme1 scheme2 scheme3 Total
310000 246000 0 0 0 0 0 246000 0 556000
Financial Sanction Details
Financial\Administrative Sanction No: 21/58 Financial\Administrative Sanction Date 16/2/2016
Fin. Sanc. Amt. (in Rs) NREGA:556000 Scheme 1
0
Scheme 2
0
Scheme 3
0
Total
556000
S.NoActivity taken upon musterollQuantityUnit PriceTotal
1signboard000
2Site clearance, cutting grass, raking into heaps and removing off the premises25601.74352
3Dag-beling-Single spade stroke minimum 75mm deep12000.3360
4Transportation of metal 1202.83112.41135210.1203
5Transportation of metal 185.4412.0276388.508
6Providing and laying reinforced cement concrete pipes N.P.2 for culverts including pointing ends, and fixing collar with cement martar 1:2 complete.-600mm dia30964.428932
7Compaction of embankment with approved materials as per clause 301.4 & 301.5 of specifications for rural roads(MORD), already spreaded at site, obtained from roadway cutting, excavated from drains, foundation of other structures or from borrow pit, making735.4221.615885.072
8Compaction of soil for construction of subgrade & earthen shoulders with approved material, already spreaded at site, obtained from roadway cutting, drains, foundation of other structures or barrow pits, i/c making 4% camber and required grade by tractor624.1823.114418.558
9Earth work in bulk excavation (exceeding 30cm in depth, 1.5m in width as well as 10sqm on plan) including disposal of excavated soil lead upto 20m and lift upto 1.5m, disposed soil to be levelled and neatly dressed - Dense or hard soil for Well Work367.7187.332101.083
10Collection of puddle earth including stacking at quarry1202.83121.3145903.279
11Collection of hard moorum including stacking at quarry.185.4140.726085.78
12contingency14400044000
13Labour difference in case of old SoR20015931800
Total Activity 556000
S.NoMaterialQuantityUnit PriceTotal
1Compaction of Earth Work735.4216.912428.598
2Compaction of GSB185.461.511402.1
3Compaction of Selected soil624.1819.912421.182
4contigency12800028000
5Display board159345934
6hume pipe12280022800
7Transportanion of hard Muram185.4369.6368529.402
8Transportation Of Earth Work1202.8370.0284222.1566
Total Material 246000