State: MADHYA PRADESH District: BHIND Block: ATER Panchayat: GOARKALAN
Work Code: 1702001025/RC/22012034230716 (Gravel road jabasa sunarpura road to Janjari pura)
Work Category: Rural Connectivity
Note:
Total Material cost and Total Activity cost shown absolute value which is multiples of 100/1000!
Financial Year : 2014-2015 Execution Level : GP
Execution Agency : Gram Panchayat(3) Work Status : Approve
Included in Annual Plan : Yes Perspective Plan : Yes
Proposal Date : 27/5/2014 Work start date : 29/9/2014
Present status : No Road Proposed Status : Gravel Road
Tech Sanction Details
Technical Sanction No. : 7933 Sanction Date : 12/7/2014
Estimated Cost as per Tech. Detl (in Rs.)
Unskilled Material Contingency Total
Est. Material Cost Est. Skilled Cost Est. Semi-Skilled Cost Scheme1 scheme2 scheme3 Total
356000 236000 0 0 0 0 0 236000 0 592000
Financial Sanction Details
Financial\Administrative Sanction No: 01/7933 Financial\Administrative Sanction Date 15/8/2014
Fin. Sanc. Amt. (in Rs) NREGA:592000 Scheme 1
0
Scheme 2
0
Scheme 3
0
Total
592000
S.NoActivity taken upon musterollQuantityUnit PriceTotal
1signboard125002500
2Jungle clearance including uprooting of rank vegetation, grass, brush wood, saplings and tree not exceeding 30cm girth and removing not exceeding 50meters outside the periphery of the area cleared.36004.114760
3Chain and compass survey.-Canals/Roads0.4584233.6
4Fly levelling for fixing temporary bench marks.-Above 15 m interval0.4438175.2
5Levelling - Headwork.-Below 5 m interval0.41460584
6Levelling - Headwork.-Above 15 m interval0.4467186.8
7Stacking and boxing.-Moorum or sand240153600
8Transportation rates for Moorum, sand, earth, surkhi, fly ash, cement and mortars.1175400175400
9Transportation rates for Hume pipes (NP-3) 800 mm to 900 mm dia.140004000
10Labour only for moorum, kankar, shingle/ gravel/red bajri spreading levelling to gradient and required camber including dressing.24080.519320
11Rolling & Compaction of granular sub-base of well graded material, spreading in uniform layers with tractor mounted grader on prepared surface, mixing by mix in place, sprinkling of water till OMC, and compacting with smooth wheel rollers of 80 to 100 kN24059.714328
12Providing and laying reinforced cement concrete pipes N.P.3 for culverts including pointing ends, and fixing collar with cement martar 1:2 complete.-900 mm dia.153684.155261.5
13Compaction of embankment with approved materials as per clause 301.4 & 301.5 of specifications for rural roads(MORD), already spreaded at site, obtained from roadway cutting, excavated from drains, foundation of other structures or from borrow pit, making95820.719830.6
14Compaction of soil for construction of subgrade & earthen shoulders with approved material, already spreaded at site, obtained from roadway cutting, drains, foundation of other structures or barrow pits, i/c making 4% camber and required grade by tractor123722.127337.7
15Earth work in bulk excavation (exceeding 30cm in depth, 1.5m in width as well as 10sqm on plan) including disposal of excavated soil lead upto 20m and lift upto 1.5m, disposed soil to be levelled and neatly dressed -Dense or hard soil for Road Work219581.2178234
16Collection of hard moorum including stacking at quarry.240130.831392
17contingency12000020000
18Labour difference in case of old SoR12388823888
Total Activity 592000
S.NoMaterialQuantityUnit PriceTotal
11904 transportion rcc hump pip140004000
2Board120002000
3Compaction of Earth Work95820.719830.6
4Compaction of GSB24059.714328
5Compaction of Selected soil123722.127337.7
6contangency and work charges150005000
7hume pipe15355053250
8Kilometre Stone (200 M)63342004
9Transportation charges1108000108000