State: MADHYA PRADESH District: REWA Block: SIRMOUR Panchayat: JIWAR
Work Code: 1713003015/IF/1000018863 (कपिलधारा कूप निर्माण कुवर बहादुर सिंह TS 66 )
Work Category: Drought Proofing
Note:
Total Material cost and Total Activity cost shown absolute value which is multiples of 100/1000!
Financial Year : 2012-2013 Execution Level : GP
Execution Agency : Gram Panchayat(3) Work Status : Approve
Included in Annual Plan : Perspective Plan :
Proposal Date : 14/4/2012 Work start date : 1/6/2013
Present status : Not Exist Proposed Status : Well
Tech Sanction Details
Technical Sanction No. : 66/15 Sanction Date : 20/5/2012
Estimated Cost as per Tech. Detl (in Rs.)
Unskilled Material Contingency Total
Est. Material Cost Est. Skilled Cost Est. Semi-Skilled Cost Scheme1 scheme2 scheme3 Total
155000 180000 0 0 0 0 0 180000 0 335000
Financial Sanction Details
Financial\Administrative Sanction No: 4/15 Financial\Administrative Sanction Date 24/5/2012
Fin. Sanc. Amt. (in Rs) NREGA:335000 Scheme 1
0
Scheme 2
0
Scheme 3
0
Total
335000
S.NoActivity taken upon musterollQuantityUnit PriceTotal
1Work charge18967.688967.68
2Pumping out water caused by springs tidal or river seepage, broken water mains or drains or well point pumping and the like.15051.67740
3Providing and laying in foundation, plinth and under floors cement concrete with 40mm nominal size graded stone aggregates (metal) i/c ramming in layers and curing complete excluding cost of form work-C.C. 1:2:4 (1cement, 2sand, 4metal)0.432530.51088.115
4Providing and laying in foundation, plinth and under floors cement concrete with 40mm nominal size graded stone aggregates (metal) i/c ramming in layers and curing complete excluding cost of form work-C.C. 1:3:6 (1cement, 3sand, 6metal)0.31865.9559.77
5Providing and placing in position RCC for roof, beams, columns column footing lintels chhajjas, balcony, stairs etc, excluding cost of reinforcement & centring but including finishing & curing.-CC 1:2:4 (1cement, 2sand, 4graded stone aggregate 20 mm nominal size)2.562660.26810.112
6Random / uncoursed rubble masonry in plinth and foundation including levelling up with cement concrete 1:6:12 (1cement, 6coarse sand, 12 aggregate 20mm nominal size) at plinth level.-In Cement mortar 1:6 (1cement, 6sand)80.161590.9127526.544
7Extra rate for C.R./ R.R./ U.C.R. stone masonry in super structure above plinth level upto floor two level.66.7143.59571.45
8Class 25 open bhatta or pajawa burnt brick masonry in plinth and foundation.-Cement mortar 1:6 (1cement, 6sand)2.671759.54697.865
915mm thick cement plaster on rough side of wall in-Cement mortar 1:4 (1cement, 4sand)22.3583.41863.99
10Pointing on random rubble masonry or uncoursed stone masonry with cement mortar 1:4 (1cement, 4sand)-Flush pointing163.4619967.4
11Collection of stone chips. quarry spalls or rubble (maximum size 0.004cum) Black trap, basalt or granite.-Other then black trap Basalt or granite10.894.21017.36
12Transportation of metal 157652.5957652.59
13Labour only for boulder soling hand packed excluding consolidation.10.888.7957.96
14Labour only for spreading, hand packing, and levelling to gradient and required camber as per MOST 2004 clause 404.3.3 of metal grading-2 & 3 as per MOST 2004 clause 400.2.5 including dressing.11.6246.5540.33
15Earth work for well excavation including disposal or stacking of excavated soil lead upto 50m lift upto 1.5m-Hard rock requiring chiselling (where blasting is prohibited)18.84667.712579.468
16Earth work in bulk excavation (exceeding 30cm in depth, 1.5m in width as well as 10sqm on plan) including disposal of excavated soil lead upto 20m and lift upto 1.5m, disposed soil to be levelled and neatly dressed.-oose or soft soil for Well Work29.4367.81995.354
17Earth work in bulk excavation (exceeding 30cm in depth, 1.5m in width as well as 10sqm on plan) including disposal of excavated soil lead upto 20m and lift upto 1.5m, disposed soil to be levelled and neatly dressed - Dense or hard soil for Well Work9.811061039.86
18Earth work in bulk excavation (exceeding 30cm in depth, 1.5m in width as well as 10sqm on plan) including disposal of excavated soil lead upto 20m and lift upto 1.5m, disposed soil to be levelled and neatly dressed- Dense or hard soil for Tank Work21.4467.81453.632
19Earth work in bulk excavation (exceeding 30cm in depth, 1.5m in width as well as 10sqm on plan) including disposal of excavated soil lead upto 20m and lift upto 1.5m, disposed soil to be levelled and neatly dressed.Hard moorum for Well Work39.24129.85093.352
20Earth work in bulk excavation (exceeding 30cm in depth, 1.5m in width as well as 10sqm on plan) including disposal of excavated soil lead upto 20m and lift upto 1.5m, disposed soil to be levelled and neatly dressed.Hard moorum for Tank Work20.5595.21956.36
21Earth work in bulk excavation (exceeding 30cm in depth, 1.5m in width as well as 10sqm on plan) including disposal or stacking of excavated soil lead upto 20m and lift upto 1.5m, disposed soil to be levelled and neatly dressed.Disintegrated or soft rock (not requiring blasting) for Well Work156.96426.5466949.7184
22Collection of hard metal other then black trap basalt and granite for road works (without blasting) including stacking as per MOST 1995, clause 400.2.5-Grading-2 (Size ranging from 63 mm to 45 mm)4.01314.21259.942
23Collection of hard metal other then black trap basalt and granite for road works (without blasting) including stacking as per MOST 1995, clause 400.2.5-Grading-3 (Size ranging from 53 mm to 22.4 mm)4.01380.71526.607
24Collection of sand including screening, washing, stacking and all leads and lifts up to the loading point.3.6116.2418.32
25SIGN BOARD115001500
262502 Earth work in bulk excavation (exceeding 30cm in depth, 1.5m in width as well as 10sqm on plan) including disposal of excavated soil lead upto 20m and lift upto 1.5m, disposed soil to be levelled and neatly dressed. (b) ii Dense or hard soil for Well Work 167.867.8
Total Activity 335000
S.NoMaterialQuantityUnit PriceTotal
1Board115001500
2Cement(bori)22025055000
3CEMENT.1250250
4Contagecny18967.688967.68
5Masonry Stone8080064000
6Sand48.19102549394.75
Total Material 180000