S.No | Activity taken upon musteroll | Quantity | Unit Price | Total |
1 | Transportation of metal | 465 | 78.39 | 36451.35 |
2 | Compaction of soil for construction of subgrade & earthen shoulders with approved transported material collected and stacked at site, i/c spreading, making 4% camber and required gradient by tractor mounted grader or labourers, watering at OMC and compact | 960 | 33.2 | 31872 |
3 | SIGN BOARD | 1 | 3800 | 3800 |
4 | Lossening of hard soil by ploughing the existing gound | 1535 | 2.7 | 4144.5 |
5 | Lossening of hard soil by ploughing the existing goundSpreading, dressing , breaking of clods of ploudged earth upto 20 m, lead and lift upto 1.5 mt, disposed soil to be leveled and neatly dressed | 1535 | 50 | 76750 |
6 | contingency | 1 | 32982.15 | 32982.15 |