S.No | Activity taken upon musteroll | Quantity | Unit Price | Total |
1 | Dag-beling-Single spade stroke minimum 75mm deep | 205 | 0.5 | 102.5 |
2 | Filling in plinth with sand under floors including watering, ramming, consolidating and dressing complete. | 24.14 | 537.3 | 12970.422 |
3 | Providing and laying in foundation, plinth and under floors cement concrete with 40mm nominal size graded stone aggregates (metal) i/c ramming in layers and curing complete excluding cost of form work-C.C. 1:4:8 (1cement, 4sand, 8metal) | 24.15 | 3067.2 | 74072.88 |
4 | False work for R.C.C. and P.C.C. work in plinth and foundation | 31 | 129 | 3999 |
5 | Providing and filling in position blown bitumen in expansion joints (10cm deep and 1cm Wide) | 58 | 6.2 | 359.6 |
6 | Add if Lead is more than 5.00Km-For every 0.5 Kms. Lead beyond 30 Kms. and part there of upto 50 Kms. | 20.14 | 703.1 | 14160.434 |
7 | Transportation rates for Moorum, sand, earth, surkhi, fly ash, cement and mortars. | 1 | 18500 | 18500 |
8 | Field Technical Supervisior Charge-FTSC | 1 | 2850 | 2850 |