S.No | Activity taken upon musteroll | Quantity | Unit Price | Total |
1 | Earth work in excavation in trenches for foundations and for pipes, cables etc. not exceeding 1.5m in width and for shafts, cesspits and the like not exceeding 10sqm on plan including dressing of sides and ramming of bottoms lift upto 1.5m including getti-Dense or hard soil | 3.64 | 59 | 214.76 |
2 | Add to or deduct from the rate for bore holes of 3.5metre depths, if the bore-holes are made deeper or shallower than 3.5metres.-300mm | 0.72 | 120.5 | 86.76 |
3 | Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundation etc. in layers not exceeding 20cm in depth consolidating each deposited layers by ramming and watering lead upto 50m and lift upto 1.5m | 0.32 | 2073.5 | 663.52 |
4 | Class 25 open bhatta or pajawa burnt brick masonry in plinth and foundation.-Cement mortar 1:5 (1cement, 5sand) | 0.6 | 1940.5 | 1164.3 |
5 | Add for masonry in supper structure above plinth level up to floor two level | 0.14 | 2054.5 | 287.63 |
6 | Half brick masonry in class 25 open bhatta or pajawa burnt brick in super structure including placing of 6mm iron bar at every 3rd layer of brick.-In cement mortar 1:4 | 6.5 | 280.3 | 1821.95 |
7 | Providing and fixing on Wall face Asbestos Cement building pipe of the following nominal size including jointing with sun yarn soaked in bitumen and cement mortar 1:2 (1cement, 2sand) complete .-100 mm dia. | 1.5 | 89.9 | 134.85 |