S.No | Activity taken upon musteroll | Quantity | Unit Price | Total |
1 | Jungle clearance including uprooting of rank vegetation, grass, brush wood, saplings and tree not exceeding 30cm girth and removing not exceeding 50meters outside the periphery of the area cleared. | 2925 | 1.4 | 4095 |
2 | Chain and compass survey.-Canals/Roads | 1.3 | 636 | 826.8 |
3 | Levelling - Headwork.-Below 5 m interval | 1.3 | 1590 | 2067 |
4 | Levelling - Headwork.-Above 15 m interval | 1.3 | 508.8 | 661.44 |
5 | Stacking without boxing.-Puddle earth, moorum, sand or kankar | 1829.61 | 11.5 | 21040.515 |
6 | Transportation of metal | 1829.61 | 91.17 | 166805.5437 |
7 | Labour only for moorum, kankar, shingle/ gravel/red bajri spreading levelling to gradient and required camber including dressing. | 2609.61 | 44.7 | 116649.567 |
8 | Providing and laying reinforced cement concrete pipes N.P.2 for culverts including pointing ends, and fixing collar with cement martar 1:2 complete.-300mm dia | 20 | 315.4 | 6308 |
9 | Compaction of embankment with approved materials as per clause 301.4 & 301.5 of specifications for rural roads(MORD), already spreaded at site, obtained from roadway cutting, excavated from drains, foundation of other structures or from borrow pit, making | 676 | 31.5 | 21294 |
10 | Compaction of soil for construction of subgrade & earthen shoulders with approved material, already spreaded at site, obtained from roadway cutting, drains, foundation of other structures or barrow pits, i/c making 4% camber and required grade by tractor | 1729 | 33.2 | 57402.8 |
11 | Construction of gravel surface course by naturally occurred gravel or river born material or by crushed metal or mixture of two or more in appropriate grading confirming to clause 2.2.2.2, plasticity characteristics of fines as per clause 2.2.3 of IRC:SP: | 234 | 388.4 | 90885.6 |
12 | Site clearance, cutting grass, raking into heaps and removing off the premises | 1 | 2000 | 2000 |
13 | Earth work in bulk excavation (exceeding 30cm in depth, 1.5m in width as well as 10sqm on plan) including disposal of excavated soil lead upto 20m and lift upto 1.5m, disposed soil to be levelled and neatly dressed -Dense or hard soil for Road Work | 3355.95 | 88.4 | 296665.98 |
14 | Earth work in excavation in trenches for foundations and for pipes,cables etc.not exceeding 1.5 m in width and for shafts,cesspits and the like not exceeding 10 sqm on plan including dressing of sides and ramming of bottoms lift upto 1.5m including gettin-Loose or soft soil | 5 | 334 | 1670 |
15 | Earth work in excavation in trenches for foundations and for pipes,cables etc.not exceeding 1.5 m in width and for shafts,cesspits and the like not exceeding 10 sqm on plan including dressing of sides and ramming of bottoms lift upto 1.5m including gettin-Dense or hard soil | 3 | 687 | 2061 |
16 | Collection of hard moorum including stacking at quarry. | 234 | 142.5 | 33345 |
17 | Rolling & Compaction of granule sub-base of well graded-material Spreading in unformed layers with tractor mounted grader on prepared surface, mixing by mix in place, sprinkling of water till OMC and compacting with Smooth wheel rollers of 80 to 100 KN static weight to achieve the desired density, complete as pet Technical Specification Clause 401 of Specification for Rural Roads i/c all leads of water etc, complete. | 780 | 65.5 | 51090 |
18 | Setting out work (Reference pillars referencing bench mark and temporary bench mark):Painting/Marking of Reference/Working Bench Mark over existing permanent structure Fixing of Reference pegs made of local rough wood for making centre line and toe lines. Fixing of reference poles made of bamboos or jungle wood bellies etc. | 12458.5 | 1.3 | 16196.05 |
19 | Field Technical Supervisior Charge-FTSC | 1 | 89000 | 89000 |