S.No | Activity taken upon musteroll | Quantity | Unit Price | Total |
1 | signboard | 1 | 1500 | 1500 |
2 | Work charge | 1 | 15000 | 15000 |
3 | Pumping out water caused by springs tidal or river seepage, broken water mains or drains or well point pumping and the like. | 60 | 56 | 3360 |
4 | Providing and laying in foundation, plinth and under floors cement concrete with 40mm nominal size graded stone aggregates (metal) i/c ramming in layers and curing complete excluding cost of form work-C.C. 1:2:4 (1cement, 2sand, 4metal) | 5.21 | 3007.5 | 15669.075 |
5 | Random / uncoursed rubble masonry in plinth and foundation including levelling up with cement concrete 1:6:12 (1cement, 6coarse sand, 12 aggregate 20mm nominal size) at plinth level.-In Lime mortar 1:2 (1lime putty, 2sand) | 5.21 | 1690.4 | 8806.984 |
6 | Extra rate for C.R./ R.R./ U.C.R. stone masonry in super structure above plinth level upto floor two level. | 92.21 | 148.3 | 13674.743 |
7 | Class 25 open bhatta or pajawa burnt brick masonry in plinth and foundation.-Lime Mortar 1: 2(1lime, 2sand) | 5.41 | 2074.6 | 11223.586 |
8 | Pointing on random rubble masonry or uncoursed stone masonry with cement mortar 1:4 (1cement, 4sand)-Flush pointing | 5.41 | 67.3 | 364.093 |
9 | Transportation of metal | 1200 | 121.3 | 145560 |
10 | Add in item No. 2402 for lift. (In well excavation)-For every 0.50 m after 1.5 m initial depth upto 6.0 m | 1 | 10000 | 10000 |
11 | 1902 Transportion of metal | 700 | 208.4 | 145880 |