State: MADHYA PRADESH District: DHAR Block: BADNAWAR Panchayat: Borda
Work Code: 1722001008/IF/9926743932 (पशु शेड रतन नंदा)
Work Category: Drought Proofing
Note:
Total Material cost and Total Activity cost shown absolute value which is multiples of 100/1000!
Financial Year : 2014-2015 Execution Level : GP
Execution Agency : Gram Panchayat(3) Work Status : Approve
Included in Annual Plan : Perspective Plan :
Proposal Date : 1/4/2014 Work start date : 7/7/2014
Present status : Existing Proposed Status : Cattle Shed
Tech Sanction Details
Technical Sanction No. : 100/008 Sanction Date : 7/5/2014
Estimated Cost as per Tech. Detl (in Rs.)
Unskilled Material Contingency Total
Est. Material Cost Est. Skilled Cost Est. Semi-Skilled Cost Scheme1 scheme2 scheme3 Total
14889.65 56980.21 0 0 0 0 0 57000 0 71869.86
Financial Sanction Details
Financial\Administrative Sanction No: 71/008 Financial\Administrative Sanction Date 8/5/2014
Fin. Sanc. Amt. (in Rs) NREGA:71870 Scheme 1
0
Scheme 2
0
Scheme 3
0
Total
71900
S.NoActivity taken upon musterollQuantityUnit PriceTotal
1Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundation etc. in layers not exceeding 20cm in depth consolidating each deposited layers by ramming and watering lead upto 50m and lift upto 1.5m3.8535.8137.83
2Providing and laying in foundation, plinth and under floors cement concrete with 40mm nominal size graded stone aggregates (metal) i/c ramming in layers and curing complete excluding cost of form work-C.C. 1:2:4 (1cement, 2sand, 4metal)2.292806.66427.114
3Providing and laying in foundation, plinth and under floors cement concrete with 40mm nominal size graded stone aggregates (metal) i/c ramming in layers and curing complete excluding cost of form work-C.C. 1:3:6 (1cement, 3sand, 6metal)2.8921906329.1
4False work for R.C.C. and P.C.C. work in plinth and foundation19.92127.12531.832
5Class 25 open bhatta or pajawa burnt brick masonry in plinth and foundation.-Cement mortar 1:8 (1cement, 8sand)6.832324.215874.286
6Providing and placing in position tested steel for R.C.C. work including cutting, bending, binding etc. as per drawings and placing in position complete up to floor two level including cost of binding wire and all wastage etc. complete.-Mild steel and Medium tensile steel bars179.9253.69643.712
710mm thick cement plaster on fair side of wall in-Cement mortar 1:5 (1cement, 5sand)19.7170.41387.584
815mm thick cement plaster on rough side of wall in-Cement mortar 1:5 (1cement, 5sand)19.7194.51862.595
9Providing 6mm thick corrugated asbestos cement sheets roofing fixed with galvanised iron J or L hooks bolts and nuts 8mm dia. G.I. plain and bitumen washer complete excluding the cost of purlines rafters and trusses.27.47266.77326.249
10Cement concrete flooring 1:2:4 (1cement, 2sand, 4graded stone aggregate, 20mm nominal size) laid in one layer and finished with floating coat of neat cement.-50 mm thick.21.09200.74232.763
11White washing whith lime on undecorated wall surfaces (3coats) to give an even shade including thoroughly broomed the surface to remove all dirt, dust, mortar drops and other foreign matter.39.427.1279.882
12Providing and laying in trenches galvanised mild steel tubes (medium grade) of the following nominal bore, tube fittings (earth work in trenches to be measured and paid for separately)-65 mm dia.36.5252.99230.85
13Earth work in bulk excavation (exceeding 30cm in depth, 1.5m in width as well as 10sqm on plan) including disposal of excavated soil lead upto 20m and lift upto 1.5m, disposed soil to be levelled and neatly dressed -Loose or soft soil for Tank Work081.20
14Earth work in bulk excavation (exceeding 30cm in depth, 1.5m in width as well as 10sqm on plan) including disposal of excavated soil lead upto 20m and lift upto 1.5m, disposed soil to be levelled and neatly dressed -Dense or hard soil for Road Work15.5581.21262.66
15contingency242112421
16Labour difference in case of old SoR201462920
Total Activity 71900
S.NoMaterialQuantityUnit PriceTotal
120 M.M. B.T. METAL1.95469.15914.8425
240 M.M. METAL (cum)2.6332.47864.422
3AC seet27.47235.66471.932
4BRICK34152.58537.5
5CEMENT (Beg)4828513680
6Centering and shuttering SQM19.9292.41840.608
7Contangancy242112421
8Display board8001800
9Gi pipe 65 mm36.5237.58668.75
10sand motor8.65472.954091.0175
11STEEL179.9248.38690.136
Total Material 57000