S.No | Activity taken upon musteroll | Quantity | Unit Price | Total |
1 | Site clearance, cutting grass, raking into heaps and removing off the premises | 56 | 25.31 | 1417.36 |
2 | Jungle clearance including uprooting of rank vegetation, grass, brush wood, saplings and tree not exceeding 30cm girth and removing not exceeding 50meters outside the periphery of the area cleared. | 6840 | 4.1 | 28044 |
3 | Earth work in bulk excavation (exceeding 30cm in depth, 1.5m in width as well as 10sqm on plan) including disposal or stacking of excavated soil lead upto 50m lift upto 1.5m-Disintegrated or soft rock (not requiring blasting) | 37.21368 | 224 | 8335.86432 |
4 | Extra for every additional Lead beyond 50metres or part thereof upto 200 m for every 50 m lead | 777.8 | 87.6 | 68135.28 |
5 | Providing and laying in foundation, plinth and under floors cement concrete with 40mm nominal size graded stone aggregates (metal) i/c ramming in layers and curing complete excluding cost of form work-C.C. 1:2:4 (1cement, 2sand, 4metal) | 30.944865 | 3296 | 101994.27504 |
6 | Providing and laying in foundation, plinth and under floors cement concrete with 40mm nominal size graded stone aggregates (metal) i/c ramming in layers and curing complete excluding cost of form work-C.C. 1:3:6 (1cement, 3sand, 6metal) | 3.2064 | 2478.2 | 7946.10048 |
7 | False work for R.C.C. and P.C.C. work in plinth and foundation | 97.7332 | 154.2 | 15070.45944 |
8 | Collection of approved soil having CBR not less than 5, including stacking at quarry. | 273.6 | 118.8 | 32503.68 |
9 | Stacking without boxing.-Puddle earth, moorum, sand or kankar | 877.8 | 10.5 | 9216.9 |
10 | Collection of sand including screening, washing, stacking and all leads and lifts up to the loading point. | 112.8 | 182.4 | 20574.72 |
11 | Transportation of metal | 182.4 | 169.6 | 30935.04 |
12 | Transportation rates for Moorum, sand, earth, surkhi, fly ash, cement and mortars. | 1051.4 | 94.32 | 99168.048 |
13 | Labour only for moorum, screening or binding material as per MOST 2004 clause 400.2.6 spreading on boulder or WBM coat as per MOST 2004 clause 404.2.7 | 1333.8 | 23.6 | 31477.68 |
14 | Rolling & Compaction of granular sub-base of well graded material, spreading in uniform layers with tractor mounted grader on prepared surface, mixing by mix in place, sprinkling of water till OMC, and compacting with smooth wheel rollers of 80 to 100 kN | 456 | 34.1 | 15549.6 |
15 | Providing and filling in foundation trenches and at the back of abutments, wing walls etc. and below pipe bed in layers not exceeding 15cm thick including watering and compacting including all lead and lifts.-Good local sand free from earth. | 22.516742 | 379.3 | 8540.6002406 |
16 | Providing and laying reinforced cement concrete pipes N.P.3 for culverts including pointing ends, and fixing collar with cement martar 1:2 complete.-900 mm dia. | 7.5 | 3900 | 29250 |
17 | Compaction of embankment with approved materials as per clause 301.4 & 301.5 of specifications for rural roads(MORD), already spreaded at site, obtained from roadway cutting, excavated from drains, foundation of other structures or from borrow pit, making | 1009.81 | 19.1 | 19287.371 |
18 | Compaction of soil for construction of subgrade & earthen shoulders with approved material, already spreaded at site, obtained from roadway cutting, drains, foundation of other structures or barrow pits, i/c making 4% camber and required grade by tractor | 2270.12 | 20.4 | 46310.448 |
19 | Earth work in bulk excavation (exceeding 30cm in depth, 1.5m in width as well as 10sqm on plan) including disposal of excavated soil lead upto 20m and lift upto 1.5m, disposed soil to be levelled and neatly dressed. | 3110.38 | 81.2 | 252562.856 |
20 | Earth work in bulk excavation (exceeding 30cm in depth, 1.5m in width as well as 10sqm on plan) including disposal of excavated soil lead upto 20m and lift upto 1.5m, disposed soil to be levelled and neatly dressed -Dense or hard soil for Road Work | 12.40456 | 97.7 | 1211.925512 |
21 | work charge | 1 | 21000 | 21000 |