S.No | Activity taken upon musteroll | Quantity | Unit Price | Total |
1 | (a) C.C. 1:2:4 (1cement, 2sand, 4metal) | 21.6 | 3816.21851851852 | 82430.32 |
2 | (b) C.C. 1:3:6 (1cement, 3sand, 6metal) | 151.34 | 3162.88608431347 | 478671.18 |
3 | Plum cement concrete 1:2:4 with 75% graded metal of 40mm size and 25% plums of 150mm size. | 19.8 | 2547.99393939394 | 50450.28 |
4 | Centering and shuttering including strutting , propping etc. and removal of form work for P.C.C. work in foundation, footing, bases for column | 200.4 | 160.519710578842 | 32168.15 |
5 | (XVIII) 16 Km. Lead | 154.61 | 399.510251600802 | 61768.28 |
6 | (XVIII) 16 Km. Lead | 99 | 256.828080808081 | 25425.98 |
7 | Site clearance, cutting grass, raking into heaps and removing off the premises | 450 | 2.62546666666667 | 1181.46 |
8 | c (iii) Hard moorum for Tank Work | 92.6 | 178.737796976242 | 16551.12 |
9 | a (i) Disintegrated or soft rock (not requiring blasting) for Tank Work | 64.12 | 568.948222083593 | 36480.96 |