S.No | Activity taken upon musteroll | Quantity | Unit Price | Total |
1 | Ordinary shrub jungle (areas below 25% covered by shrubs) clearance involving removal of grass. Shrubs, bushes and twigs, excluding uprooting (for survey works) | 2460 | 0.98 | 2410.8 |
2 | Surface dressing of ground, including removing vegetation, and/ or unequalities not exceeding 15cm deep and disposal of rubbish lead upto 50m And lift upto1.5m-Dense or hard soil | 1230 | 9.32 | 11463.6 |
3 | Collection of approved soil having CBR not less then 12, including stacking at quarry. | 246 | 211.55 | 52041.3 |
4 | Transportation rates for Moorum, sand, earth, surkhi, fly ash, cement and mortars. | 543 | 210.63 | 114372.09 |
5 | Rolling & Compaction of granular sub-base of well graded material, spreading in uniform layers with tractor mounted grader on prepared surface, mixing by mix in place, sprinkling of water till OMC, and compacting with smooth wheel rollers of 80 to 100 kN | 297.6 | 62.72 | 18665.472 |
6 | Providing and laying reinforced cement concrete pipes N.P.2 for culverts including pointing ends, and fixing collar with cement martar 1:2 complete.-300mm dia | 10 | 435.47 | 4354.7 |
7 | Compaction of soil for construction of subgrade & earthen shoulders with approved transported material collected and stacked at site, i/c spreading, making 4% camber and required gradient by tractor mounted grader or labourers, watering at OMC and compact | 246 | 24.06 | 5918.76 |
8 | Construction of gravel surface course by naturally occurred gravel or river born material or by crushed metal or mixture of two or more in appropriate grading confirming to clause 2.2.2.2, plasticity characteristics of fines as per clause 2.2.3 of IRC:SP: | 98.4 | 958 | 94267.2 |
9 | Collection of sand including screening, washing, stacking and all leads and lifts up to the loading point. | 297.6 | 185.38 | 55169.088 |
10 | SIGN BOARD | 1 | 6627.1 | 6627.1 |
11 | contingency | 1 | 11082 | 11082 |
12 | 2507. KM Stone (A) With Rainforced CC (ii) Ordinary KM Stone | 1 | 1617.6 | 1617.6 |
13 | 2507. KM Stone (A) With Rainforced CC (ii) 200 M Stone | 4 | 491.83 | 1967.32 |