S.No | Activity taken upon musteroll | Quantity | Unit Price | Total |
1 | Site clearance, cutting grass, raking into heaps and removing off the premises | 10 | 20 | 200 |
2 | Transportation rates for Moorum, sand, earth, surkhi, fly ash, cement and mortars. | 1000 | 92.16 | 92160 |
3 | Compaction of soil for construction of subgrade & earthen shoulders with approved material, already spreaded at site, obtained from roadway cutting, drains, foundation of other structures or barrow pits, i/c making 4% camber and required grade by tractor | 2500 | 24.7 | 61750 |
4 | Lossening of hard soil by ploughing the existing gound | 3000 | 2.7 | 8100 |
5 | Lossening of hard soil by ploughing the existing goundSpreading, dressing , breaking of clods of ploudged earth upto 20 m, lead and lift upto 1.5 mt, disposed soil to be leveled and neatly dressed | 3000 | 50 | 150000 |