Work Code: 1711006047/RC/22012034208721 (KHET SADAK YOJANA PATPARA GHAT SE KAMODA RAIKWAR KE GHAR TAK)
Work Category: Rural Connectivity
Note:
Total Material cost and Total Activity cost shown absolute value which is multiples of 100/1000!
Financial Year : 2013-2014 Execution Level : GP
Execution Agency : Gram Panchayat(3) Work Status : Approve
Included in Annual Plan : Yes Perspective Plan : Yes
Proposal Date : 26/1/2014 Work start date : 26/1/2014
Present status : No Road Proposed Status : Gravel Road
Tech Sanction Details
Technical Sanction No. : 47/494 Sanction Date : 14/2/2014
Estimated Cost as per Tech. Detl (in Rs.)
Unskilled Material Contingency Total
Est. Material Cost Est. Skilled Cost Est. Semi-Skilled Cost Scheme1 scheme2 scheme3 Total
676000 409000 0 0 0 0 0 409000 0 1085000
Financial Sanction Details
Financial\Administrative Sanction No: AS/47/16 Financial\Administrative Sanction Date 26/2/2014
Fin. Sanc. Amt. (in Rs) NREGA:1085000 Scheme 1
0
Scheme 2
0
Scheme 3
0
Total
1085000
S.NoActivity taken upon musterollQuantityUnit PriceTotal
1signboard160006000
2Jungle clearance including uprooting of rank vegetation, grass, brush wood, saplings and tree not exceeding 30cm girth and removing not exceeding 50meters outside the periphery of the area cleared.47554.119495.5
3Providing and laying in foundation, plinth and under floors cement concrete with 40mm nominal size graded stone aggregates (metal) i/c ramming in layers and curing complete excluding cost of form work-C.C. 1:2:4 (1cement, 2sand, 4metal)233089.971067.7
4Providing and laying in foundation, plinth and under floors cement concrete with 40mm nominal size graded stone aggregates (metal) i/c ramming in layers and curing complete excluding cost of form work-C.C. 1:3:6 (1cement, 3sand, 6metal)32404.17212.3
5Add to item No. 0413 and 0415 if in place of 40mm metal.-If 20 mm graded metal is used23169.43896.2
6False work for R.C.C. and P.C.C. work in plinth and foundation100164.116410
7TRANSPORTATION OF MATERIAL211.8981000211898
8Stacking and boxing.-Metal, single or gravel42025.610752
9Stacking without boxing.-Puddle earth, moorum, sand or kankar1669.510.517529.75
10Loading of metal in truck, dumper etc.1669.529.248749.4
11Unloading of metal in truck, dumper etc.1669.514.624374.7
12Labour only for moorum, kankar, shingle/ gravel/red bajri spreading levelling to gradient and required camber including dressing.1669.54168449.5
13Providing and laying reinforced cement concrete pipes N.P.2 for culverts including pointing ends, and fixing collar with cement martar 1:2 complete.-300mm dia20312.96258
14Providing and laying reinforced cement concrete pipes N.P.3 for culverts including pointing ends, and fixing collar with cement martar 1:2 complete.-1000 mm dia.7.5355526662.5
15Compaction of embankment with approved materials as per clause 301.4 & 301.5 of specifications for rural roads(MORD), already spreaded at site, obtained from roadway cutting, excavated from drains, foundation of other structures or from borrow pit, making189022.642714
16Compaction of soil for construction of subgrade & earthen shoulders with approved material, already spreaded at site, obtained from roadway cutting, drains, foundation of other structures or barrow pits, i/c making 4% camber and required grade by tractor1669.52440068
17Earth work in bulk excavation (exceeding 30cm in depth, 1.5m in width as well as 10sqm on plan) including disposal of excavated soil lead upto 20m and lift upto 1.5m, disposed soil to be levelled and neatly dressed -Dense or hard soil for Road Work189081.2153468
18Collection of hard moorum including stacking at quarry.1753.59130.8229369.572
19Collection/Excavation of Gravel Material meeting the requirements of Hard moorum as detailed in RES SOR chapter No. 03 Notes Clause 3.2(C) including stacking and all leads and lifts up to the loading point at quarry.252130.832961.6
20Collection of river Borne material (RBM)(any mixture of sand & gravel)i/c boxing and all leads and lifts up to the loading point at quarry.168114.319202.4
21Rolling & Compaction of granule sub-base of well graded-material Spreading in unformed layers with tractor mounted grader on prepared surface, mixing by mix in place, sprinkling of water till OMC and compacting with Smooth wheel rollers of 80 to 100 KN static weight to achieve the desired density, complete as pet Technical Specification Clause 401 of Specification for Rural Roads i/c all leads of water etc, complete.42061.525830
22Setting out work (Reference pillars referencing bench mark and temporary bench mark):Painting/Marking of Reference/Working Bench Mark over existing permanent structure Fixing of Reference pegs made of local rough wood for making centre line and toe lines. Fixing of reference poles made of bamboos or jungle wood bellies etc.0.73276.62293.62
Total Activity 1085000
S.NoMaterialQuantityUnit PriceTotal
140 mm Metal35001500
2BGSY SIGN BOARD160006000
3Cement18030054000
4Centering and Shuttering100959500
5Compaction of Earth Work18902241580
6Compaction of GSB4206125620
7compaction of sub grad earthen22292453496
8HumePipes7.5360027000
9Kilometre Stone (200 M)43501400
10Kilometre Stone (ordinary)27001400
11PhotoCopy & Stationary110001000
12Transportation charges1151284151284
13गिटी 20 mm24100024000
14रेत1385011050
Total Material 409000