State: MADHYA PRADESH District: REWA Block: GANGEV Panchayat: DHAUDHKI
Work Code: 1713004045/RC/22012034291031 (खेत सड़क प्रधानमंत्री रोड से राममणि द्विवेदी के घर तक)
Work Category: Rural Connectivity
Note:
Total Material cost and Total Activity cost shown absolute value which is multiples of 100/1000!
Financial Year : 2015-2016 Execution Level : GP
Execution Agency : Gram Panchayat(3) Work Status : Approve
Included in Annual Plan : Yes Perspective Plan : Yes
Proposal Date : 2/10/2015 Work start date : 25/11/2015
Present status : No Road Proposed Status : Bitumen Top
Tech Sanction Details
Technical Sanction No. : 1513/045 Sanction Date : 23/11/2015
Estimated Cost as per Tech. Detl (in Rs.)
Unskilled Material Contingency Total
Est. Material Cost Est. Skilled Cost Est. Semi-Skilled Cost Scheme1 scheme2 scheme3 Total
380000 308000 0 0 0 0 0 308000 0 688000
Financial Sanction Details
Financial\Administrative Sanction No: 02/045 Financial\Administrative Sanction Date 24/11/2015
Fin. Sanc. Amt. (in Rs) NREGA:688000 Scheme 1
0
Scheme 2
0
Scheme 3
0
Total
688000
S.NoActivity taken upon musterollQuantityUnit PriceTotal
1signboard115001500
2Site clearance, cutting grass, raking into heaps and removing off the premises32001.75440
3Dag-beling-Single spade stroke minimum 75mm deep15000.3450
4Transportation of metal 1603.045119.07190874.56815
5Transportation of metal 231.75412.0295485.635
6Providing and laying reinforced cement concrete pipes N.P.2 for culverts including pointing ends, and fixing collar with cement martar 1:2 complete.-600mm dia30971.429142
7Compaction of embankment with approved materials as per clause 301.4 & 301.5 of specifications for rural roads(MORD), already spreaded at site, obtained from roadway cutting, excavated from drains, foundation of other structures or from borrow pit, making919.02521.619850.94
8Compaction of soil for construction of subgrade & earthen shoulders with approved material, already spreaded at site, obtained from roadway cutting, drains, foundation of other structures or barrow pits, i/c making 4% camber and required grade by tractor780.2323.118023.313
9Earth work in bulk excavation (exceeding 30cm in depth, 1.5m in width as well as 10sqm on plan) including disposal of excavated soil lead upto 20m and lift upto 1.5m, disposed soil to be levelled and neatly dressed - Dense or hard soil for Well Work229.7587.320057.175
10Collection of puddle earth including stacking at quarry1603.405121.3194493.0265
11Transportion of metal140.7231.7532607.225
12Barbed wire Fixing only231.7561.514252.625
13Labour difference in case of old SoR38916764963
Total Activity 688000
S.NoMaterialQuantityUnit PriceTotal
1CEMENT.10000
2Compaction19.91833.7536491.625
3contangency and work charges12900029000
4Display board160006000
5pipe12800028000
6soil transportation70.021604.045112315.2309
7transportation of hard muram 1231.75412.0295485.635
Total Material 308000