S.No | Activity taken upon musteroll | Quantity | Unit Price | Total |
1 | Filling foundation or under floor with 40mm gauge graded metal and moorum including ramming in layers and watering. | 56.7 | 862 | 48875.4 |
2 | Providing and laying in foundation, plinth and under floors cement concrete with 40mm nominal size graded stone aggregates (metal) i/c ramming in layers and curing complete excluding cost of form work-C.C. 1:2:4 (1cement, 2sand, 4metal) | 28.35 | 3307.4 | 93764.79 |
3 | False work for R.C.C. and P.C.C. work in plinth and foundation | 56.25 | 147.8 | 8313.75 |
4 | Coursed rubble masonry second sort in plinth and foundation.-In Lime mortar 1:2 (1lime putty, 2sand) | 151.2 | 2082.1 | 314813.52 |
5 | Pointing on random rubble masonry or uncoursed stone masonry with cement mortar 1:4 (1cement, 4sand)-Flush pointing | 336 | 127.6 | 42873.6 |
6 | Transportation of metal | 43.09 | 183.7 | 7915.633 |
7 | Transportation of metal | 24.08 | 288.7 | 6951.896 |
8 | Transportation of sand | 65.99 | 377.7 | 24924.423 |
9 | Transportation rates for Masonry stone. | 151.2 | 257.18 | 38885.616 |
10 | Transportation rates for Boulders, Laterite, rubble pitching stones and excavated hard rock. | 18.67 | 177.9 | 3321.393 |
11 | Transportation rates for Moorum, sand, earth, surkhi, fly ash, cement and mortars. | 12.73 | 291.3 | 3708.249 |
12 | Lossening of hard soil by ploughing the existing gound | 302.4 | 52.7 | 15936.48 |
13 | contingency | 1 | 715.25 | 715.25 |