S.No | Activity taken upon musteroll | Quantity | Unit Price | Total |
1 | signboard | 1 | 2000 | 2000 |
2 | Jungle clearance including uprooting of rank vegetation, grass, brush wood, saplings and tree not exceeding 30cm girth and removing not exceeding 50meters outside the periphery of the area cleared. | 5950 | 4.1 | 24395 |
3 | Contingency | 20.45 | 1000 | 20450 |
4 | Earth work in bulk excavation (exceeding 30cm in depth, 1.5m in width as well as 10sqm on plan) including disposal of excavated soil lead upto 50m and lift upto 1.5m, disposed soil to be levelled and neatly dressed.-Hard moorum | 10 | 86.1 | 861 |
5 | Extra for every additional Lead beyond 50metres or part thereof upto 200 m for every 50 m lead | 1100 | 21.9 | 24090 |
6 | Providing and laying in foundation, plinth and under floors cement concrete with 40mm nominal size graded stone aggregates (metal) i/c ramming in layers and curing complete excluding cost of form work-C.C. 1:2:4 (1cement, 2sand, 4metal) | 10.5 | 3089.9 | 32443.95 |
7 | Random / uncoursed rubble masonry in plinth and foundation including levelling up with cement concrete 1:6:12 (1cement, 6coarse sand, 12 aggregate 20mm nominal size) at plinth level.-In Cement mortar 1:8 (1cement, 8sand) | 35.5 | 1835.3 | 65153.15 |
8 | TRANSPORTATION OF MATERIAL | 155.5 | 1000 | 155500 |
9 | Labour only for item no.1035, 1036 and 1037-Raised and cut pointing | 30.05 | 114.9 | 3452.745 |
10 | 22cm thick dry stone picked up boulder pitching i/c picking of boulder with individual size of 22cm depth. | 430.5 | 136.1 | 58591.05 |
11 | Add extra item no. 1274 for quarried boulder pitching. | 430.5 | 107.3 | 46192.65 |
12 | Collection of puddle earth including stacking at quarry | 295 | 90.2 | 26609 |
13 | Transportation charges of water for every additional 200m or part thereof, beyond initial lead of 200m up to 2 Km. Lead for | 295 | 3.2 | 944 |
14 | Preparation of sub grade by excavating earth work to the 15cm average depth, dressing to camber including making good the undulations etc. and disposal of surplus earth with lead upto 50metres and upto 1.5metre.-Dence or hard soil | 2850 | 10.2 | 29070 |
15 | FOR EARTHEN DAM - Puddle filling of good clay including lead upto 50m including mixing watering and kneeding by tamping ramming and laying etc. | 295 | 262.5 | 77437.5 |
16 | Earth work in bulk excavation (exceeding 30cm in depth, 1.5m in width as well as 10sqm on plan) including disposal of excavated soil lead upto 20m and lift upto 1.5m, disposed soil to be levelled and neatly dressed.-oose or soft soil for Well Work | 5005 | 81.2 | 406406 |
17 | Collection of hard moorum including stacking at quarry. | 55.5 | 130.8 | 7259.4 |