S.No | Activity taken upon musteroll | Quantity | Unit Price | Total |
1 | Earth work in bulk excavation (exceeding 30cm in depth, 1.5m in width as well as 10sqm on plan) including disposal of excavated soil lead upto 50m and lift upto 1.5m, disposed soil to be levelled and neatly dressed.-Dense or hard soil | 13.2 | 136.3 | 1799.16 |
2 | Earth work in bulk excavation (exceeding 30cm in depth, 1.5m in width as well as 10sqm on plan) including disposal of excavated soil lead upto 50m and lift upto 1.5m, disposed soil to be levelled and neatly dressed.-Hard moorum | 15.6 | 181.45 | 2830.62 |
3 | Earth work in bulk excavation (exceeding 30cm in depth, 1.5m in width as well as 10sqm on plan) including disposal or stacking of excavated soil lead upto 50m lift upto 1.5m-Disintegrated or soft rock (not requiring blasting) | 27.2 | 317.75 | 8642.8 |
4 | Providing and laying in foundation, plinth and under floors cement concrete with 40mm nominal size graded stone aggregates (metal) i/c ramming in layers and curing complete excluding cost of form work-C.C. 1:2:4 (1cement, 2sand, 4metal) | 69.2 | 3829.11 | 264974.412 |
5 | Providing and laying in foundation, plinth and under floors cement concrete with 40mm nominal size graded stone aggregates (metal) i/c ramming in layers and curing complete excluding cost of form work-C.C. 1:3:6 (1cement, 3sand, 6metal) | 14.8 | 3175.78 | 47001.544 |
6 | Plum cement concrete 1:2:4 with 75% graded metal of 40mm size and 25% plums of 150mm size. | 22 | 2561.75 | 56358.5 |
7 | False work for R.C.C. and P.C.C. work in plinth and foundation | 216 | 172 | 37152 |
8 | Steel work in single section including in cutting, hoisting fixing in position in R.S. joists, channels, angles, tee. | 1210 | 74.76 | 90459.6 |
9 | work charge | 3 | 1000 | 3000 |