S.No | Activity taken upon musteroll | Quantity | Unit Price | Total |
1 | (b) C.C. 1:3:6 (1cement, 3sand, 6metal) | 170.49 | 3159.36870197666 | 538640.77 |
2 | Plum cement concrete 1:3:6 with 75% graded metal of 40mm size and 25% plums of 150mm size. | 41.6 | 2313.87259615385 | 96257.1 |
3 | Centering and shuttering including strutting , propping etc. and removal of form work for P.C.C. work in foundation, footing, bases for column | 264.73 | 156.781022173535 | 41504.64 |
4 | (XII) 7 Km. Lead | 294 | 198.119965986395 | 58247.27 |
5 | Site clearance, cutting grass, raking into heaps and removing off the premises | 600 | 2.62545 | 1575.27 |
6 | b (iii) Dense or hard soil for Tank Work | 49.95 | 134.187587587588 | 6702.67 |
7 | c (iii) Hard moorum for Tank Work | 2253.25 | 178.737752135804 | 402740.84 |