S.No | Activity taken upon musteroll | Quantity | Unit Price | Total |
1 | signboard | 1 | 1500 | 1500 |
2 | Work charge | 1 | 12602 | 12602 |
3 | Earth work in bulk excavation (exceeding 30cm in depth, 1.5m in width as well as 10sqm on plan) including disposal of excavated soil lead upto 50m and lift upto 1.5m, disposed soil to be levelled and neatly dressed.-Loose or soft soil | 270 | 41.12 | 11102.4 |
4 | Providing and laying in foundation, plinth and under floors cement concrete with 40mm nominal size graded stone aggregates (metal) i/c ramming in layers and curing complete excluding cost of form work-C.C. 1:3:6 (1cement, 3sand, 6metal) | 36 | 1565.91 | 56372.76 |
5 | Random / uncoursed rubble masonry in plinth and foundation including levelling up with cement concrete 1:6:12 (1cement, 6coarse sand, 12 aggregate 20mm nominal size) at plinth level.-In Cement mortar 1:4 (1cement, 4sand) | 144 | 1549.19 | 223083.36 |
6 | Providing and placing in position tested steel for R.C.C. work including cutting, bending, binding etc. as per drawings and placing in position complete up to floor two level including cost of binding wire and all wastage etc. complete.-Mild steel and Medium tensile steel bars | 30 | 2133.91 | 64017.3 |
7 | Transportation of metal | 1 | 97431 | 97431 |
8 | Labour difference in case of old SoR | 1 | 16000 | 16000 |