S.No | Activity taken upon musteroll | Quantity | Unit Price | Total |
1 | signboard | 1 | 2000 | 2000 |
2 | Surface dressing of ground, including removing vegetation, and/ or unequalities not exceeding 15cm deep and disposal of rubbish lead upto 50m And lift upto1.5m-Loose or soft soil | 4 | 32000 | 128000 |
3 | Providing and laying in foundation, plinth and under floors cement concrete with 40mm nominal size graded stone aggregates (metal) i/c ramming in layers and curing complete excluding cost of form work-C.C. 1:2:4 (1cement, 2sand, 4metal) | 4 | 38000 | 152000 |
4 | Providing and laying in trenches galvanised mild steel tubes (medium grade) of the following nominal bore, tube fittings (earth work in trenches to be measured and paid for separately)-15 mm dia. | 4 | 32000 | 128000 |
5 | Lossening of hard soil by ploughing the existing goundSpreading, dressing , breaking of clods of ploudged earth upto 20 m, lead and lift upto 1.5 mt, disposed soil to be leveled and neatly dressed | 5 | 20000 | 100000 |