S.No | Activity taken upon musteroll | Quantity | Unit Price | Total |
1 | Dag-beling-Single spade stroke minimum 75mm deep | 1 | 22478 | 22478 |
2 | Filling foundation or under floor with 40mm gauge graded metal and moorum including ramming in layers and watering. | 13.5 | 882 | 11907 |
3 | Providing and laying in foundation, plinth and under floors cement concrete with 40mm nominal size graded stone aggregates (metal) i/c ramming in layers and curing complete excluding cost of form work-C.C. 1:2:4 (1cement, 2sand, 4metal) | 10.13 | 3307.4 | 33503.962 |
4 | False work for R.C.C. and P.C.C. work in plinth and foundation | 20 | 147.8 | 2956 |
5 | Coursed rubble masonry second sort in plinth and foundation.-In Cement mortar 1:8 (1cement, 8sand) | 45 | 2082.1 | 93694.5 |
6 | Pointing on random rubble masonry or uncoursed stone masonry with cement mortar 1:4 (1cement, 4sand)-Raised and cut pointing | 100 | 127.6 | 12760 |
7 | Lossening of hard soil by ploughing the existing gound | 108 | 52.7 | 5691.6 |
8 | contingency | 1 | 18996 | 18996 |