S.No | Activity taken upon musteroll | Quantity | Unit Price | Total |
1 | Jungle clearance including uprooting of rank vegetation, grass, brush wood, saplings and tree not exceeding 30cm girth and removing not exceeding 50meters outside the periphery of the area cleared. | 1140 | 6.54194736842105 | 7457.82 |
2 | Filling foundation, around masonry work, plinth, sides of foundation etc. with moorum I/c ramming layers not exceeding 20cm in depth consolidating each deposited layers by ramming and watering lead upto 50m and lift upto 1.5m. | 356.16 | 273.446203953279 | 97390.6 |
3 | (a) C.C. 1:2:4 (1cement, 2sand, 4metal) | 11.09 | 3812.70153291253 | 42282.86 |
4 | (c) C.C. 1:4:8 (1cement, 4sand, 8metal) | 0.99 | 2818.87878787879 | 2790.69 |
5 | (k) Cement mortar 1:8 (1cement, 8sand) | 6.6 | 3741.25757575758 | 24692.3 |
6 | (d) Cement mortar 1:6 (1cement, 6sand) | 26.4 | 99.4878787878788 | 2626.48 |
7 | (XV) 10 Km. Lead | 0.91 | 233.043956043956 | 212.07 |
8 | (XXIX) 50 Km. Lead | 9.42 | 567.267515923567 | 5343.66 |
9 | (X) 5.0 Km. Lead | 356.16 | 152.11278638814 | 54176.49 |
10 | (XV) 10 Km. Lead | 2.54 | 210.070866141732 | 533.58 |
11 | (XXIX) 50 Km. Lead | 5.21 | 510.149712092131 | 2657.88 |
12 | Compaction of soil for construction of subgrade & earthen shoulders with approved transported material collected and stacked at site, i/c spreading, making 4% camber and required gradient by tractor mounted grader or labourers, watering at OMC and compacted by 80 to 100 kN static weight rollers to achieve desired density minimum 100% of the MDD as per IS:2720 (Part-7). Complete compaction work as per specifications for rural roads (MORD) clause 303, i/c required leads and lifts of materials etc. complete. | 319.2 | 23.9325814536341 | 7639.28 |
13 | (b) Dense or hard soil | 2.97 | 146.026936026936 | 433.7 |
14 | Citizen Information Board Size 0.9 Meter x 1.2 Meter ( Community Works ) | 1 | 3578.36 | 3578.36 |