S.No | Activity taken upon musteroll | Quantity | Unit Price | Total |
1 | Labour only for moorum, kankar, shingle/ gravel/red bajri spreading levelling to gradient and required camber including dressing. | 0 | 0 | 0 |
2 | Earth work in excavation in trenches for foundations and for pipes,cables etc.not exceeding 1.5 m in width and for shafts,cesspits and the like not exceeding 10 sqm on plan including dressing of sides and ramming of bottoms lift upto 1.5m including gettin-Dense or hard soil | 182 | 25 | 4550 |
3 | contingency | 1 | 1016 | 1016 |
4 | Applying chemicles in soil around plants Mandays per hundred. | 420 | 60 | 25200 |
5 | Layout of Field for per digging of pits for plantation work. | 1000 | 0.5 | 500 |
6 | Preperation of pits for plantation of poly plants including mixing of soil manure fertilizer and insecticides with first watering etc. complete. | 420 | 15 | 6300 |
7 | Supply of vermi compost | 140 | 7.5 | 1050 |
8 | Supply of singal super phosphate (SSP) | 35 | 6.08 | 212.8 |
9 | Supply of muriate of potash (MOP) | 17.5 | 16.98 | 297.15 |
10 | Supply of urea. | 17.5 | 6 | 105 |
11 | Supply of Themate, phorate 10 G pesticites | 3.5 | 65 | 227.5 |
12 | Supply of foresty or horticulture Plant cost 3 to5 feet . height | 210 | 30 | 6300 |