State: MADHYA PRADESH District: BHIND Block: ATER Panchayat: SAURA
Work Code: 1702001008/RC/22012034215269 (Pahuch Margh Nirman Shiv Singh ke makan se suresh )
Work Category: Rural Connectivity
Note:
Total Material cost and Total Activity cost shown absolute value which is multiples of 100/1000!
Financial Year : 2013-2014 Execution Level : GP
Execution Agency : Gram Panchayat(3) Work Status : Approve
Included in Annual Plan : Yes Perspective Plan : Yes
Proposal Date : 27/1/2014 Work start date : 3/3/2014
Present status : No Road Proposed Status : Gravel Road
Tech Sanction Details
Technical Sanction No. : 7231 Sanction Date : 24/2/2014
Estimated Cost as per Tech. Detl (in Rs.)
Unskilled Material Contingency Total
Est. Material Cost Est. Skilled Cost Est. Semi-Skilled Cost Scheme1 scheme2 scheme3 Total
314000 172000 0 0 0 0 0 172000 0 486000
Financial Sanction Details
Financial\Administrative Sanction No: 07/7231 Financial\Administrative Sanction Date 25/2/2014
Fin. Sanc. Amt. (in Rs) NREGA:486000 Scheme 1
0
Scheme 2
0
Scheme 3
0
Total
486000
S.NoActivity taken upon musterollQuantityUnit PriceTotal
1signboard125002500
2Jungle clearance including uprooting of rank vegetation, grass, brush wood, saplings and tree not exceeding 30cm girth and removing not exceeding 50meters outside the periphery of the area cleared.31504.112915
3Chain and compass survey.-Canals/Roads0.35584204.4
4Fly levelling for fixing temporary bench marks.-Above 15 m interval0.35438153.3
5Levelling - Headwork.-Below 5 m interval0.351460511
6Levelling - Headwork.-Above 15 m interval0.35467163.45
7Stacking and boxing.-Moorum or sand210153150
8Transportation rates for Moorum, sand, earth, surkhi, fly ash, cement and mortars.1187000187000
9Labour only for moorum, kankar, shingle/ gravel/red bajri spreading levelling to gradient and required camber including dressing.21080.516905
10Rolling & Compaction of granular sub-base of well graded material, spreading in uniform layers with tractor mounted grader on prepared surface, mixing by mix in place, sprinkling of water till OMC, and compacting with smooth wheel rollers of 80 to 100 kN21059.712537
11Compaction of embankment with approved materials as per clause 301.4 & 301.5 of specifications for rural roads(MORD), already spreaded at site, obtained from roadway cutting, excavated from drains, foundation of other structures or from borrow pit, making838.1720.717350.119
12Compaction of soil for construction of subgrade & earthen shoulders with approved material, already spreaded at site, obtained from roadway cutting, drains, foundation of other structures or barrow pits, i/c making 4% camber and required grade by tractor1045.4522.123104.445
13Earth work in bulk excavation (exceeding 30cm in depth, 1.5m in width as well as 10sqm on plan) including disposal of excavated soil lead upto 20m and lift upto 1.5m, disposed soil to be levelled and neatly dressed -Dense or hard soil for Road Work192181.2155985.2
14Collection of hard moorum including stacking at quarry.210130.827468
15contingency12561125611
Total Activity 486000
S.NoMaterialQuantityUnit PriceTotal
1Board120002000
2Compaction of Earth Work838.1720.717350.119
3Compaction of GSB21059.712537
4Compaction of Selected soil1045.4522.123104.445
5contangency and work charges12661126611
6Kilometre Stone (200 M)33341002
7Kilometre Stone (ordinary)26871374
8Transportation charges12000020000
9Transportation of embankment s14300043000
10Transportation of GSB12500025000
Total Material 172000