S.No | Activity taken upon musteroll | Quantity | Unit Price | Total |
1 | (I) Lead upto 100 Metres | 921.6 | 38.8887261284722 | 35839.85 |
2 | (III) Lead upto 200 meters | 1512 | 116.643121693122 | 176364.4 |
3 | Providing and laying in foundation, plinth and under floors cement concrete with 20mm nominal size graded stone aggregates (metal) i/c ramming in layers and curing complete excluding cost of form work ( if 20 mm metal is used in place of 40mm metal in item number 04.13 & 04.15)
(a) C.C. 1:2:4 (1cement, 2sand, 4metal) | 44.1 | 3947.4514739229 | 174082.61 |
4 | (X) 5.0 Km. Lead | 840 | 198.552595238095 | 166784.18 |
5 | Labour only for boulder soling hand packed excluding consolidation. | 756 | 199.717526455026 | 150986.45 |
6 | Site clearance, cutting grass, raking into heaps and removing off the premises | 1400 | 2.81891428571429 | 3946.48 |
7 | (c) Dense or hard soil (PT/30/30) | 294 | 212.40112244898 | 62445.93 |
8 | Collection of quarried stone or rubble. Maximum size 0.014 cum. | 756 | 311.201997354497 | 235268.71 |
9 | Stacking of Gravel or Hard Moorum at site without Boxing. | 756 | 23.3286243386243 | 17636.44 |
10 | Citizen Information Board Size 0.9 Meter x 1.2 Meter ( Community Works ) | 1 | 3682 | 3682 |