Work Code: 1830001013/RC/1234736895 (RC पांदण रस्ता परशुराम सुर्यवंशी ते विजय मांडवकर यांच्या शेतापर्यंत ग्रा.प. अमिर्झा)
Work Category: Rural Connectivity
Note:
Total Material cost and Total Activity cost shown absolute value which is multiples of 100/1000!
Financial Year : 2023-2024 Execution Level : GP
Execution Agency : Gram Panchayat (3) Work Status : Approve
Included in Annual Plan : Yes Perspective Plan : Yes
Proposal Date : 28/11/2023 Work start date : 1/12/2023
Present status : Earthern road Proposed Status : Repair and maintenance of WBM Roads for Community
Tech Sanction Details
Technical Sanction No. : 1830001/2023-2024/297238/TS Sanction Date : 6/12/2023
Estimated Cost as per Tech. Detl (in Rs.)
Unskilled Material Contingency Total
Est. Material Cost Est. Skilled Cost Est. Semi-Skilled Cost Scheme1 scheme2 scheme3 Total
626742.59 1172990.95 2538.75 3510.75 0 0 0 1180000 23266 1829049.04
Financial Sanction Details
Financial\Administrative Sanction No: 1830001/2023-2024/297238/AS Financial\Administrative Sanction Date 6/12/2023
Fin. Sanc. Amt. (in Rs) NREGA:1829049 Scheme 1
0
Scheme 2
0
Scheme 3
0
Total
1830000
S.NoActivity taken upon musterollQuantityUnit PriceTotal
1900 mm dia R.C.C. pipe303765.71112971.3
2Excavation in earth for all sorts of soil & silt, lime, shadu, sand/ grit, such types of strata including dressing and conveying the excavated material by head and upto a distance of 10m and laying or spreading or filling in furrahas in layers of 30cm thick upto lift of 1:50m as directed. (A) Excavation - (In General) Rate for the area2978.585116.024998447249345590.32
3Excavation in earth for soft murum type of strata including dressing and converying the excavated material by head load upto a distance of 10m and laying or spereading or filling in furrahas in layers of 30cm. Thick upto a lift of 1.50m as directed. (A) Excavation - (In General) rate for the othe area744.69146.328002255972108969
4Additional rate of additional lead by head load for all kind of soil, sand, soft murum, hard murum, stones, pebbles,boulders, rock. (Additional lead of 10 m. in other area)1414.8426.863200079160938007.13
5Additional rate of additional lead by head load for all kind of soil, sand, soft murum, hard murum, stones, pebbles,boulders, rock. (Additional lead of 20 m. in other area)446.7949.686004610667222199.21
6Constucting casing or Hearting at embankment site with the following sorts of materials conveyed, removing trees, bushes, grass roots, etc. breaking clods and spreading the same in layers for embankement with earth work and dressing upto required level. (A) For Soil, soft murum and hard murum and boulder materials. For General area.2792.41510.919999355396730493.17
7Cleaning the sides of land as directed and removing the roots up to 20 cm. circumference and disposing off all this material up to a 10m distance. Rate for the other area20006.27912558
8Supplying soft murum at the road site, including conveying and stacking complete.880348.907954545455307039
9Spreading hard murum/soft murum/gravel or kankar for side width complete.88031.833920454545528013.85
10Compacting the subgrade /gravel/oversize metal (200mm loose) layers for all widths with vibratory roller having weight 8 to 10 MT including necessary, labour, materials and artificial watering etc complete.440042.46186824
11Lum sum Material for all works.4308481430848
Total Activity 1624000
S.NoMaterialQuantityUnit PriceTotal
10367-Portland Cement0.1476000882
20983-Fine sand (zone IV)0.1981600316.8
31710-R.C.C. pipes NP2 class 900 mm dia30329998970
41724-R.C.C. collars NP2 class 900 mm dia123584296
52209-Cement0.14700
62261-Fine sand (1 part badarpur sand : 2 parts jamuna sand0.19800
72331-R.C.C. pipes 900 mm dia3000
83-Display Board / CIB150005000
94-Conveyance11044310443
105-GST1166827.23166827.23
117-Worksite facilities/Creche/Drinking water/First aid11741617416
129-Quality control and Survey158505850
13MR6321-soft murum880313275440
14MR6533-Material cost Rs 1/- per unit.4308481430848
15MR6556-8 to 10 MT Vibratory Roller for 200mm Loose metal440037162800
Total Material 1180000