S.No | Activity taken upon musteroll | Quantity | Unit Price | Total |
1 | Transportation rates for Moorum, sand, earth, surkhi, fly ash, cement and mortars. | 1000 | 78.39 | 78390 |
2 | Compaction of soil for construction of subgrade & earthen shoulders with approved transported material collected and stacked at site, i/c spreading, making 4% camber and required gradient by tractor mounted grader or labourers, watering at OMC and compact | 2500 | 33.2 | 83000 |
3 | Lossening of hard soil by ploughing the existing gound | 3000 | 2.7 | 8100 |
4 | Lossening of hard soil by ploughing the existing goundSpreading, dressing , breaking of clods of ploudged earth upto 20 m, lead and lift upto 1.5 mt, disposed soil to be leveled and neatly dressed | 2500 | 50 | 125000 |
5 | contingency | 1 | 58510 | 58510 |