S.No | Activity taken upon musteroll | Quantity | Unit Price | Total |
1 | (I) Lead upto 100 Metres | 148.688 | 42.1294253739374 | 6264.14 |
2 | (III) Lead upto 200 meters | 148.688 | 126.36339180028 | 18788.72 |
3 | Steel work welded in built up sections, framed work, including cutting hoisting fixing in position in gratings, frames, guard bars, ladders, railing, brackets and similar works & trusses and trussed purlins up to 25m span and 15 m over all height | 149.25 | 107.319061976549 | 16017.37 |
4 | (c) Masonry stones, pitching stones or boulders | 148.688 | 50.5703217475519 | 7519.2 |
5 | Labour only for boulder soling hand packed excluding consolidation. | 80.719 | 215.827748113827 | 17421.4 |
6 | (a) Boulders | 67.969 | 927.348644234872 | 63030.96 |
7 | b (iii) Dense or hard soil for Tank Work | 10.453 | 156.081507701138 | 1631.52 |
8 | a (i) Disintegrated or soft rock (not requiring blasting) for Tank Work | 16.725 | 659.777578475336 | 11034.78 |
9 | Collection of boulders at source (maximum size 0.014cum) without quarrying i.e. picked up boulders. | 148.688 | 187.297495426665 | 27848.89 |