The Mahatma Gandhi National Rural Employment Guarantee Act 27-Sep-2024 05:08:38 PM 
Back  
State: MADHYA PRADESH District: REWA Block: GANGEV Panchayat: TIKURI -32
Work Code: 1713004067/RC/22012034341013 (Sudur sampark sadak PM Road se Shantidham ki taraf 650 Metter )
Work Category: Rural Connectivity
Note:
Total Material cost and Total Activity cost shown absolute value which is multiples of 100/1000!
Financial Year : 2017-2018 Execution Level : GP
Execution Agency : Gram Panchayat(3) Work Status : Approve
Included in Annual Plan : Yes Perspective Plan : Yes
Proposal Date : 14/4/2017 Work start date : 9/6/2017
Present status : No Road Proposed Status : Gravel Road
Tech Sanction Details
Technical Sanction No. : 4317/146771/01 Sanction Date : 14/4/2017
Estimated Cost as per Tech. Detl (in Rs.)
Unskilled Material Contingency Total
Est. Material Cost Est. Skilled Cost Est. Semi-Skilled Cost Scheme1 scheme2 scheme3 Total
248000 667000 0 0 0 0 0 667000 0 915000
Financial Sanction Details
Financial\Administrative Sanction No: 146771/01/01 Financial\Administrative Sanction Date 14/4/2017
Fin. Sanc. Amt. (in Rs) NREGA:915000 Scheme 1
0
Scheme 2
0
Scheme 3
0
Total
915000
S.NoActivity taken upon musterollQuantityUnit PriceTotal
1signboard120002000
2Setting out work Refferance pillers, refferancing bench mark and temporary bench mark Construction of Reference Bench Mark 50x50x70 cm. made of 1:3:6 cement concrete i/c excavation of 50x50x50 cm pit, working benchmark 30x30x45 cm at every 500 m interva11.61.6
3Lime Surkhi Mortar 1:1:2 ( 1 lime putty, 1 surkhi, 2sand )1052.7527
4Work charge120002000
5Dag-beling-Single spade stroke minimum 75mm deep23000.3690
6Labour only for 20mm thick cement plaster of any ratio.80001.814400
7Collection of approved soil having CBR not less then 12, including stacking at quarry.35052.718445
8Transportation of metal 2000119238000
9Compaction of embankment with approved materials as per clause 301.4 & 301.5 of specifications for rural roads(MORD), already spreaded at site, obtained from roadway cutting, excavated from drains, foundation of other structures or from borrow pit, making117021.625272
10Compaction of soil for construction of subgrade & earthen shoulders with approved material, already spreaded at site, obtained from roadway cutting, drains, foundation of other structures or barrow pits, i/c making 4% camber and required grade by tractor250023.157750
11Compaction of hard shoulder collected at site, i/c making 4-5% camber by tractor mounted grader or labourers, watering at OMC and compacting with 80 to 100 kN static weight rollers to achieve desired density minimum 100% of the MDD as per IS:2720 (Part-7)35040.114035
12Construction of gravel base course by naturally occurred gravel or river born material or by crushed metal or mixture of two or more to bring the material in appropriate grading confirming to clause 2.2.2.2, plasticity characteristics of fines as per clau460575264500
13Construction of gravel surface course by naturally occurred gravel or river born material or by crushed metal or mixture of two or more in appropriate grading confirming to clause 2.2.2.2, plasticity characteristics of fines as per clause 2.2.3 of IRC:SP:230508116840
14Collection of puddle earth including stacking at quarry257052.7135439
15Labour difference in case of old SoR12500025000
Total Activity 915000
S.NoMaterialQuantityUnit PriceTotal
110 mm -  M.S. rod0.153500525
28 mm -  M.S. rod235007000
3Binding wire860480
4Cement252606500
5Centering and Shuttering168305040
6Compaction3217544
7Compaction of Earth Work1.36391383086.9
8Display board110001000
9GITTI12245329436
10Gravel or moorum1100407100407
11Iron rod0.524531226.5
12Loosening Machine Rent545.232.61417.598
13pf RCC hume pipe 10002100000200000
14pipe25971.424285
15Rolling Earth & moorum221.2517.353838.6875
16Soil transport246.6563.2315595.6795
17steel purches(8mm 10mm 12mm)0.56924531395.757
18sub grade watring615009000
19Transportanion of hard Muram31663.1219945.92
20Transportation charges21663.1213633.92
21Transportation of GSB21663.1213633.92
22Transportation Of Selected Soi1111297111297
23transportion22663.1214265.12
24गिटी 20 mm124532453
25रोलर21.3517.1365.085
Total Material 667000