State: MADHYA PRADESH District: KHANDWA Block: BALADI Panchayat: SEMRUDH RAIYAT
Work Code: 1725001035/RC/22012034201347 (AANTRIK MARG SAH NALI NIRMAN KARY TIRATH KE GAR SE)
Work Category: Rural Connectivity
Note:
Total Material cost and Total Activity cost shown absolute value which is multiples of 100/1000!
Financial Year : 2013-2014 Execution Level : GP
Execution Agency : Gram Panchayat(3) Work Status : Approve
Included in Annual Plan : Yes Perspective Plan : Yes
Proposal Date : 2/8/2013 Work start date : 10/1/2014
Present status : Earthern road Proposed Status : Earthern road
Tech Sanction Details
Technical Sanction No. : 0000540/2013 Sanction Date : 10/1/2014
Estimated Cost as per Tech. Detl (in Rs.)
Unskilled Material Contingency Total
Est. Material Cost Est. Skilled Cost Est. Semi-Skilled Cost Scheme1 scheme2 scheme3 Total
76000 51000 0 0 0 0 0 51000 0 127000
Financial Sanction Details
Financial\Administrative Sanction No: 000010/201 Financial\Administrative Sanction Date 12/1/2014
Fin. Sanc. Amt. (in Rs) NREGA:127000 Scheme 1
0
Scheme 2
0
Scheme 3
0
Total
127000
S.NoActivity taken upon musterollQuantityUnit PriceTotal
1Earth work in bulk excavation (exceeding 30cm in depth, 1.5m in width as well as 10sqm on plan) including disposal of excavated soil lead upto 50m and lift upto 1.5m, disposed soil to be levelled and neatly dressed.-Loose or soft soil278.2686.2523999.925
2Earth work in bulk excavation (exceeding 30cm in depth, 1.5m in width as well as 10sqm on plan) including disposal or stacking of excavated soil lead upto 50m lift upto 1.5m-Disintegrated or soft rock (not requiring blasting)10.82242419.2
3Extra for every additional Lead beyond 50metres or part thereof upto 200 m for every 50 m lead1887.481574.64
4Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundation etc. in layers not exceeding 20cm in depth consolidating each deposited layers by ramming and watering lead upto 50m and lift upto 1.5m000
5Providing and laying in foundation, plinth and under floors cement concrete with 40mm nominal size graded stone aggregates (metal) i/c ramming in layers and curing complete excluding cost of form work-C.C. 1:2:4 (1cement, 2sand, 4metal)63177.819066.8
6Providing and laying in foundation, plinth and under floors cement concrete with 40mm nominal size graded stone aggregates (metal) i/c ramming in layers and curing complete excluding cost of form work-C.C. 1:3:6 (1cement, 3sand, 6metal)62478.214869.2
7False work for R.C.C. and P.C.C. work in plinth and foundation120154.218504
8Transportation of metal 12094.3211318.4
9Transportation of metal 5.4161.5872.1
10Transportation of metal 5.1161.5823.65
11Transportation of metal 5.28193.151019.832
12Labour only for moorum, screening or binding material as per MOST 2004 clause 400.2.6 spreading on boulder or WBM coat as per MOST 2004 clause 404.2.712023.62832
13Rolling & Compaction of granular sub-base of well graded material, spreading in uniform layers with tractor mounted grader on prepared surface, mixing by mix in place, sprinkling of water till OMC, and compacting with smooth wheel rollers of 80 to 100 kN6057.73462
14Earth work in bulk excavation (exceeding 30cm in depth, 1.5m in width as well as 10sqm on plan) including disposal of excavated soil lead upto 20m and lift upto 1.5m, disposed soil to be levelled and neatly dressed. -Loose or soft soil for Road Work1.881.2146.16
15Earth work in bulk excavation (exceeding 30cm in depth, 1.5m in width as well as 10sqm on plan) including disposal of excavated soil lead upto 20m and lift upto 1.5m, disposed soil to be levelled and neatly dressed-Hard moorum for Road Work5.497.7527.58
16Excavation in trenches for foundations and for pipes, cables, etc. not exceeding 1.5m in width and for shafts, cesspits and the like not exceeding 10 sqm on plan including dressing of sides and ramming of bottoms, lift upto 1.5m including getting out and-Disintegrated or soft rock (not requiring blasting)120118.814256
17Surface dressing of ground, including removing vegetation, and/ or unequalities not exceeding 15cm deep and disposal of rubbish lead upto 20m And lift upto1.5m-Dense or hard soil.40012.85120
18work charge154635463
Total Activity 127000
S.NoMaterialQuantityUnit PriceTotal
120 M.M. METAL58504250
240 mm Metal5.49004860
3cement Begs5229015080
4Centering and Shuttering70755250
5Hire Charges of Concrete mixer36501950
6mason parday103503500
7Mate8.51851572.5
8sand transport Trip230006000
9Transportation of hard moorum9094.328488.8
Total Material 51000