S.No | Activity taken upon musteroll | Quantity | Unit Price | Total |
1 | Jungle clearance including uprooting of rank vegetation, grass, brush wood, saplings and tree not exceeding 30cm girth and removing not exceeding 50meters outside the periphery of the area cleared. | 1957.5 | 6.64524137931034 | 13008.06 |
2 | Providing stone chips under stone pitching | 360 | 454.87925 | 163756.53 |
3 | (a) Other then black trap Basalt or granite | 90.45 | 301.75688225539 | 27293.91 |
4 | (a) Consolidation of Moorum /earth work (rate for 1Cum. of Moorum /earth work) | 3137.63 | 2.38837275268276 | 7493.83 |
5 | (XI) 6 Km. Lead | 90.45 | 262.241459369818 | 23719.74 |
6 | (III) 1.5 Km. Lead | 1023.75 | 77.9294358974359 | 79780.26 |
7 | (XII) 7 Km. Lead | 1901.25 | 179.096415516108 | 340507.06 |
8 | (XV) 10 Km. Lead | 212.63 | 210.629356158585 | 44786.12 |
9 | (a) Boulders | 112.5 | 576.088088888889 | 64809.91 |
10 | For earthen dam - puddle filling of good clay including lead upto 20 meter including mixing, watering & kneading by tamping , ramming & laying etc. | 212.63 | 428.459201429714 | 91103.28 |
11 | Hearting, casing/cut off filling soil etc.
At optimum moisture content to achieve maximum dry density by mechanical sheep foot roller/ vibratory compacters including watering, required leads and lifts and material etc. complete. | 3137.63 | 21.7850415759666 | 68353.4 |
12 | a (iii) Loose or soft soil for Tank Work | 43.74 | 100.984910836763 | 4417.08 |
13 | c (iii) Hard moorum for Tank Work | 2975.4 | 181.559924716005 | 540213.4 |
14 | a (i) Disintegrated or soft rock (not requiring blasting) for Tank Work | 53.16 | 577.376410835215 | 30693.33 |