S.No | Activity taken upon musteroll | Quantity | Unit Price | Total |
1 | Earth work in bulk excavation (exceeding 30cm in depth, 1.5m in width as well as 10sqm on plan) including disposal of excavated soil lead upto 50m and lift upto 1.5m, disposed soil to be levelled and neatly dressed.-Hard moorum | 32.4 | 155.8 | 5047.92 |
2 | Providing and laying in foundation, plinth and under floors cement concrete with 40mm nominal size graded stone aggregates (metal) i/c ramming in layers and curing complete excluding cost of form work-C.C. 1:2:4 (1cement, 2sand, 4metal) | 2 | 3175.9 | 6351.8 |
3 | Providing and laying in foundation, plinth and under floors cement concrete with 40mm nominal size graded stone aggregates (metal) i/c ramming in layers and curing complete excluding cost of form work-C.C. 1:3:6 (1cement, 3sand, 6metal) | 3.6 | 2562.8 | 9226.08 |
4 | Providing and placing in position RCC for roof, beams, columns column footing lintels chhajjas, balcony, stairs etc, excluding cost of reinforcement & centring but including finishing & curing.-CC 1:1:2 (1cement, 1sand, 2graded stone aggregate 20 mm nominal size) | 17.87 | 4488.6 | 80211.282 |
5 | False work for lintels slabs, columns, walls, sills, chhajjas balconies, beams, stair cases or ornamental moulded work, curved surface etc. cast in situ including all lead and lift | 28.8 | 204.7 | 5895.36 |
6 | False work for R.C.C. and P.C.C. work in plinth and foundation | 50.08 | 155.3 | 7777.424 |
7 | Class 25 open bhatta or pajawa burnt brick masonry in plinth and foundation.-Lime Mortar 1: 2(1lime, 2sand) | 5.56 | 3083.5 | 17144.26 |
8 | Add for masonry in supper structure above plinth level up to floor two level | 18.56 | 3303.8 | 61318.528 |
9 | Providing and placing in position tested steel for R.C.C. work including cutting, bending, binding etc. as per drawings and placing in position complete up to floor two level including cost of binding wire and all wastage etc. complete.-Mild steel and Medium tensile steel bars | 1403.26 | 52.9 | 74232.454 |
10 | 15mm thick cement plaster on rough side of wall in-Cement mortar 1:5 (1cement, 5sand) | 200 | 125.3 | 25060 |
11 | Snowcem or durocem painting of any shade-2 coats on new work | 200 | 20.3 | 4060 |
12 | Field Technical Supervisior Charge-FTSC | 1 | 88000 | 88000 |